OPERATIONAL WORKS

In accordance with Condition 1 of the Preliminary Approval for Operational Works, the Engineering and
Landscape Plans have been revised to reflect the Architectural Plans. In addition to this, the Engineering
and Landscape Plans have been amended to include the following:

    ●​ Updated stormwater and engineering drawings including:
       a. Additional detail demonstrating that the post-development peak flow rate discharging to
       structure “7/1” does not exceed the pre-development peak flow rate. The detail must clearly
       demonstrate that the development and calculations incorporate appropriate climate change
       allowances in accordance with AO2.4 of the Water Quality and Drainage Code.
       b. Additional detail confirming an appropriate climate change allowance has been applied to the
       sizing of all detention tanks.
       c. A stormwater design calculation table.
       d. Details of detention outlet orifices / controls.
       e. Engineering documentation showing the materials, stair treatment and handrails along the
       pedestrian pathway adjacent to the southern frontage;
       f. Prepared by a suitably qualified person (RPEQ)
    ●​ Updated access drawings/documents including:
       a. Appropriate manoeuvring areas for access to the car stackers in accordance with
       AS2890.1:2004 and the manufacturers specifications.
       b. Linemarkings for the car stackers.
       c. Prepared by a suitably qualified person (RPEQ).

It is requested that standard conditions are applied to the Development Permit. In addition, it is
requested that the Approved Plans table is amended to include the following plans:


  Plan No.     Rev.                     Plan/Document Name                                Date

 Landscape Plans

  S2411198       E     General notes, sheet layout and site location, prepared by       26.09.25
    LD1                Anembo Consultants

  S2411198       C     Project specifications, prepared by Anembo Consultants           26.09.25
    LD2

  S2411198       C     Project specifications, annual maintenance and finishes          26.09.25
    LD3                schedule, prepared by Anembo Consultants

  S2411198       C     Plant schedules, prepared by Anembo Consultants                  26.09.25
    LD4

  S2411198       C     Typical details, prepared by Anembo Consultants                  26.09.25
    LD5

  S2411198       C     Landscape Plan (Ground 1/2), prepared by Anembo                  26.09.25
     LP1               Consultants

  S2411198       C     Landscape Plan (Ground 2/2) and Basement, prepared by            26.09.25
     LP2               Anembo Consultants




                                                                                                        3

Used in these records

About this file

File size
290 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Representations.pdf · 290 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.