Flows from Driveways

The runoff from the driveway will be directed onto adjacent unpaved areas where
practicable to allow for infiltration. The use of a grated drain constructed at the
bottom of the ramp will catch runoff from the ramp before it flows into the
basement. Water collected in the basement will be pumped to a pit at ground
level with a system of Atlantis cells allowing the injection of the water back into
the water table. It will be designed to allow 90% of the water to soak away into
the sand, and only in times of heavy rain would the water bypass this and be
connected to the councils storm water system. Further details of this system will
be provided at the operational works phase of design.

Stormwater Qualit

It is proposed that low flows collected from the driveway will be dissipated over
unpaved areas for infiltration as much as practicable. Where runoff enters the
proposed grated drain, it will be treated by a gross pollutant trap prior to
discharge to the proposed stormwater pit at the frontage of the site.

The quality of the runoff from the development would meet the requirements of
Environmental Protection (Water) Policy ANZECC standards and Council's Code
for Waterways and Wetlands.

Stormwater Detention

In order to ensure that the site can be developed with no net increase in runoff,
an XP-STORM model was created to determine pre and post development flows.
Average recurrence intervals of 1 in 10, 20 and 100 year storm events were
analysed. It was decided that a stormwater detention tank to be located in the
basement would be used to attenuate post development flows.

2.5.1 Methodology
The hydrology and hydraulics of the Q10, Q20, and Q100 scenarios was
analysed using the XP-STORM stormwater management model with storm
patterns derived from Australian Rainfall and Runoff publication and rainfall
intensities derived for the Peregian area. To accurately determine
maximum flows, storm durations of 10, 20, 25, 30 ,45, 60, 75, 90 and 180
minutes were investigated.

2.5.2 Selection of Modelling Parameters

Used in these records

About this file

File size
19.5 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_2689 - Response to request for further Information [As Published].pdf · 19.5 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.