06/2689 - Response to request for further Information [As Published] · 132006.2689

of 126

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (19.5 MB): the original may take a few minutes to open or download. The page text below is quick to read.

4,3. It is further noted that the driveway ramp grades need to be determined based on the
inside radius of the ramp (i.e. where the ramp grades will be steeper) as opposed to the
grade at the centre of the ramp. This is outlined in the Australian Standard for Off-Street
Car Parking (AS2890.1) and will need to be addressed. _

 

 

Response

Please refer to the traffic engineering response prepared by Burchill VDM which addresses this
matter. The proposal plans prepared by Ken Down Architects namely the Basement/Site Plan
Drawing No. 2243 SD02 Revision E has been revised in line with recommendations from the
traffic engineering response.

 

 

4.4. Furthermore, the applicant will need to demonstrate in accordance with Specific
Outcome 017 of Table 14-46 of the Driveways & Carparking Code that abasement level of
RL7.1 (as presently proposed) can in fact drain by gravity means without the need for
pumping.

In this regard the applicant will need to arrange a surveyor to establish the invert levels of
Council's existing drainage system and demonstrate how the basement will be drained to
this drainage system. If this cannot be achieved the applicant will need to investigate the
option of raising the basement level (to ensure the basement can drain by gravity means)
and/or upgrading the existing Council drainage system such that it is at a level that can
drain the basement carpark. These issues will need to be resolved prior to Council issuing a
Development Permit for the proposed Material Change of Use as Council must be sure that
the development is suitable and can actually work.

 

Response
Please refer to the Stormwater Management Report prepared by Barlow Gregg VDM which
addresses this matter.

Car Parking

 

Item 5
Demonstrate that the proposed driveway and carparking area comply with all aspects of the
Australian Standard (AS2890.1) for Parking Facilities, Part 9: Off Street Car Parking.

5.1. In this regard it is noted that the present proposal contains blind corners and blind
aisles with no provision for vehicles to turn around. As such designated turning bays must
be provided and it is recommended that they be at least 3m wide (to allow ease of access
and departure) and at least 5.4m long. To this end:

.One turning bay should be provided adjacent to the proposed stairs located at the south-
eastern comer of the basement (space number 30), and

.One turning bay should be provided on the eastern side of the basement immediately to
_the north of the proposed tank (space number 22).

 

 

 

Response

Please refer to the traffic engineering response prepared by Burchill VDM which addresses this
matter. The proposal plans prepared by Ken Down Architects namely the Basement/Site Plan
Drawing No. 2243 SDO2 Revision E and Ground Floor Plan Drawing No. 2243 SD02 Revision

Used in these records

About this file

File size
19.5 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_2689 - Response to request for further Information [As Published].pdf · 19.5 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.