SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 11 AUGUST 2020
BRANCH ACTIVITIES RECENT ACHIEVEMENTS CURRENT PRIORITIES THE NEXT QUARTER
Road and Beckmans Road upgrade. Beckman’s Roads intersection
intersection upgrade. upgrade construction.
Reviewed funding agreement for
Cooroy Noosa Road and Beckman’s
Roads intersection upgrade design.
Design decisions to be documented and Design decisions are being Continue to document design Develop a program of infrastructure
reported to the RPEQ or Council as documented and reported to RPEQ. decisions and report to RPEQ. assessments based on level of risk.
required. Standards are being included in Continue to include standards in Adopt process for documenting
Include standards in construction construction drawings sets. construction drawings sets. Design decisions reporting to
drawing sets. Develop a program of
Continue to develop a process for Council.
infrastructure assessments based on
documenting design decisions
level of risk e.g. traffic volumes audit
reporting to Council.
Assess lighting compliance risk at
roundabouts & crossings etc.
Define staff roles within Project Staff roles have been defined within Continue ongoing development of Continuous improvement activities.
Management Plans and Improve current Project Management Plans. tools and procedures.
awareness of previous project lessons Lessons learnt register established Continue documenting lessons
learnt summaries. and populated from recent projects learnt summaries for completed
for future reference. projects future reference.
Provide high level corporate reporting of Quarterly risk reporting is being Continue to develop to report Continuous improvement activities.
Project Risk to PCG, CWE and Council. provided to PCG and CWE each Quarterly risk to PCG and CWE.
quarter.
Continue to refine smart sheet tool
for reporting high level corporate
reporting of Project Risk to PCG and
CWE.
Continually evolve contractor selection Consultants / contractors are Continue use of lessons learnt and Continuous improvement activities.
process. reviewed and scorecard developed contractor references database for
Develop database of lessons learnt and after project completion. completed projects.
contractor references. Lessons learnt and contractor Continue to use consultants /
Review of consultants / contractors after references database has been contractors review scorecard for key
project completion. developed for key projects. projects.
North Shore Holiday Camp designed Handover of project completed. Defects management. Defects management.
and developed for sustainable tourism. Final optimisation of bore water Continue to manage ongoing Ongoing monitoring of performance
treatment and sewer systems. revegetation works with Noosa & and costs of water treatment and
Project completed and handed over District Landcare. sewer systems.
to Corporate Services - Property
Page 67 of 100
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.