OPERATIONAL PLAN 2019-20 PROGRESS REPORT
ATTACHMENT 1
THE NOOSA ENVIRONMENT
No. Project Responsibility Update BS) fF
1 Commence implementation of the Noosa Environment Environmental Services Manager With an adopted Environment Strategy, appropriate monitoring mechanisms Completed QO
Strategy are being developed to ensure implementation proceeds. Some actions for
the first year of the implementation plan are already underway. The first
annual report on implementation actions will reported to Council soon.
2 Adopt the Noosa River Management Plan and commence Environmental Services Manager The second draft of the River Plan went out to public consultation in Behind Schedule @
implementation December 2019/January 2020 and responses have been collated. This has
been workshopped with Councillors and a Stakeholder Reference Group is
being developed to finalise and support implementation of the plan. A report
will come to Council soon outlining the Terms of Reference for the Group, as
well as summarising feedback received so far, and next steps, in the River
Plan.
3 Continue implementation of Zero Emissions Action Plan Director Environment & Sustainable Solar systems completed at Noosaville library, Noosa River Holiday Park and Completed Q
Development Cooroy Butter Factory. Australian Energy Foundation conducted two
community information sessions (on-line) - well attended by community
members. Udate of Council's free advice line for solar & batteries has been
well utilised.
4 Investigate landfill emission reduction opportunities Waste and Environmental Health Ongoing quarterly meetings with LMS regarding the implementation of Completed Qo
Manager additional vertical wells as waste deposit allows. Waste Strategy development
commenced but delayed due to COVID-19 travel restrictions.
5 ‘Establish a partnership arrangement with The Nature Director Environment & Sustainable The Project Manager for this project has been appointed by The Nature On track QO
Conservancy and initiate the planning for restoration of Development Conservancy and began in late January. The project plan was reported to
the Oyster Reefs in the Noosa River Council in July with the first annual report due in September. The project is
progressing well, despite COVID restrictions on bringing the community
together around the project. Current priorities include working with community
stakeholders around the proposed locations for the oyster ecosystems, and
meeting permit requirements of State agencies.
6 Continue the implementation of the Yurol and Ringtail Chief Executive Officer Harvesting of pine and hardwood forests continues and tracks through the Completed Qo
forestry areas transition to National Park with key partners areas have been closed. Council received an update report on this project in
July and provided in principle support for Greenfleet to undertake remediation
work.
Page 77 of 100See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.