7. All structures must use materials, natural finishes and colours that blend with the
surrounding natural landscape.
8. Structures must be designed and constructed such that they are free standing
within the waterway and are not connected to or behind the revetment wall or
rock wall.
9. Structures must be designed and constructed such that they do not place
additional vertical or lateral loads onto the existing revetment wall that may
compromise the long term stability and/or durability of the wall. Upon completion
of works, a certification by RPEQ must be provided to Council in this regard.
10. All structures must have no detrimental effects on stormwater drains and/or
easements.
11. No boatlifting devices are to be attached or moored at the structures for the
purpose of elevating a vessel above the water without Council approval.
12. The jetty and deck areas must be constructed in a manner to render the
underside area vermin proof.
13. There must be no electrical reticulation system carrying electricity in excess of
24 volts beyond the revetment wall unless all switches and power outlets are
positioned above the 1% AEP flood level.
14. Lighting associated with the use must be designed, installed, operated, and
maintained in accordance with Section 3 of AS4282 Control of the Obtrusive
Effects of Outdoor Lighting.
15. Wastewater and sullage must only be disposed of at approved pump out facilities.
16. The mooring facility must not be utilised for live-aboard purposes.
17. Any construction and post construction activity must not to impact on the
condition of the waterway and is to be conducted so as not to breach the
Environmental Protection Act EPA (1994) and the Environmental Protection
(Water) Policy 2009.
18. Certification by a Registered Professional Engineer of Queensland that states
that the jetty extension and pontoons are constructed in accordance with best
practice methods and are structurally sound must be submitted to Council. This
certification must be submitted to Council within three (3) months of the
completion of the works. A final inspection and approval of the structure by
Council’s Inspector is also required. Please contact Council’s Planning
Assessment Section to arrange the inspection.
19. After completion, the proposed works must be maintained in a sound state of
repair in accordance with the approved plans.
20. All necessary State government approvals relating to this development must be
obtained prior to any works commencing on the site.
Environment
21. To ensure the safety of persons accessing the approved works and to prevent
environmental harm, a safety audit of the on-site fuel storage tanks, bowsers and
associate pipework, valves, vents and systems shall be conducted by a suitably
qualified professional and submitted to Council for approval prior to the use of
the new works (pontoon/jetty extensions). The audit shall demonstrate that the
fuel systems are in a safe and serviceable condition or, where necessary, identify
repair and rectification requirements to meet the relevant Australian Standards
and industry best practice environmental management. Any repair works must
be completed, with certification submitted by the auditor to Council, prior to the
use of the new works (pontoon/jetty extensions).
Page 5 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.