7. Attachment F - Bushfire Hazard Assessment
Bushfire Hazard Assessment and Management Plan
Table 7: Assessment against the Noosa Plan 2020 – Bushfire Hazard Overlay Code.
Performance Outcomes Acceptable Outcomes Compliance Assessment
Safety of people and property
Development maintains the safety of Development which will materially increase the number of
people and property from the adverse people living or congregating on premises, including COMPLIES WITH PO1
impacts of bushfire. AO1.1 reconfiguring a lot, is not located within a medium or high
bushfire hazard area. The proposed new building will have an
appropriate setback for a vulnerable use, not
PO1 Development maximises setbacks from hazardous being exposed to greater than 10kW/m2 of
vegetation to achieve an acceptable risk. radiant heat.
AO1.2
Editor’s Note — PSP8 Natural Hazards provides
guidance for assessing bushfire hazard risk and
preparing a bushfire hazard management plan.
Impacts on Ecologically Important Areas
Bushfire mitigation measures do not No acceptable outcome provided
adversely impact on: COMPLIES WITH PO2
a. biodiversity values, connectivity and The development footprint will result in the
ecosystem functioning; and removal of a small number if native trees. The
b. the long term physical integrity of proposed APZ does not require any additional
PO2 waterways, wetland and areas of native native vegetation clearing. Therefore, the
vegetation. proposal will have minimal impacts on
biodiversity values, connectivity and ecosystem
functioning. The proposal will also not impact on
the long term physical of waterways, wetlands or
areas of mapped native vegetation
Water Supply for Fire Fighting Purposes
Development provides an adequate Premises are connected to the reticulated water supply.
water supply for fire fighting purpose COMPLIES WITH AO3.2
which is reliable, safely located and Editor's note—For reconfiguring a lot, water supply needs
freely accessible. AO3.1 to provide for a minimum flow and pressure of 10 litres a The proposed dwelling will have the required
PO3 second at 200kPa at all times for fire fighting purposes. minimum level of stored, dedicated, on-site
water supply for fire-fighting purposes. The site
OR has access to a 48,000-litre drinking water
AO3.2 Where there is no available reticulated water supply, the supply and an additional two (2) 5,000 litre water
PR22428_BHAMP_199 Beddington Road, Doonan Page 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.