GENERAL COMMITTEE MEETING AGENDA                                                15 OCTOBER 2018


Infrastructure Charges
Conditions 26, 27, 28 and 38 require amendments to ensure the conditions are consistent with
the Planning Act 2016. The proposed amendments also seek to clarify that the cost of the bus
stop relocation is not off settable against the charges as the bus stop is required to be relocated
by the applicant as a result of the development. The amendments to the conditions are track
changed below.
26.   Goodchap Street and Val Crescent must be upgraded for the length of their frontage to the
      subject site. The works must be undertaken in accordance with an Operational Works
      approval and must include in particular:
           reconstruction of any damaged kerb and channelling;
           construction of pedestrian footpaths in accordance with the conditions of this
           Decision Notice;
           removal of the existing property accesses and reinstatement of the kerb, footpath and
           verge area to match the balance of the site frontage, including the provision of topsoil
           and turf where the existing verge is grassed;
           relocation/reinstatement of existing on-street parking bays required as a result of
           development works;
           linemarking for any potential additional on street parking spaces.
      This Condition is imposed pursuant to s665 s145 of the Planning Act 2016 being non-trunk
      infrastructure and s646 s128 being necessary trunk infrastructure identified by Council’s
      LGIP to service the development.
27.   The existing formation in Val Crescent must be upgraded from the existing formation in
      Goodchap Street and extending to the tangent point in the kerb line adjacent to the
      northern boundary of No 3 Val Crescent. The works must be undertaken in accordance
      with an Operational Works approval and must include but not be limited to:
           works designed and constructed in accordance with Council’s Planning Scheme
           Policy PSP 5 – Engineering Design Standards – Roads, Drainage and Earthworks
           (section 3.19(d) – Industrial/Commercial – Local road);
           the full width of the formation in Val Crescent;
           reinstatement of existing linemarking.
      This Condition is imposed pursuant to s665 s145 of the Planning Act 2016 being non-trunk
      infrastructure and s646 being necessary trunk infrastructure identified by Council’s LGIP to
      service the development.
      Bus Stop relocation
28.   The bus stop and associated infrastructure must be relocated in accordance with
      Translink’s requirements. These works must also include the installation of a new shelter in
      accordance with Council’s standard drawings. In this regard please note that Council has a
      contract with a 3rd party to manufacture and install bus shelters. The developer must:
            carryout adjustment works to the kerb line and/or road linemarking along the new
           bus stop bay as necessary to achieve compliance with the applicable standards for
           cycle lanes requirements. The works must be included as part of the Operational
           Works application.
           liaise with the bus shelter manufacturer/installer and create all necessary conditions
           for their works (i.e. concrete slab, etc.);
           advise Council of timing for the installation of the bus shelter and report as soon as
           possible any changes to the programme.


                                                                                    Page 20 of 55
Log in to download the original file

2018-10-15 General Committee Agenda(PDF, 4MB).pdf · 4.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.