EHP Permit number: SPCE05212613

 

Schedule D - Noise

D1

D2

D3

Noise from the ERA must not cause an environmental nuisance at any nuisance sensitive place.

When requested by the administering authority, noise monitoring must be undertaken to investigate any
complaint of noise nuisance and the results are to be provided within 14 days to the administering
authority.

The method of measurement and reporting of noise levels must comply with the latest edition of the
Queensland Government Noise Measurement Manual.

Schedule E - Water

 

 

 

 

E1 Erosion protection measures and sediment control measures must be implemented and maintained to
minimise erosion and the release of sediment.

E2 Suitable diversion drains and/or contour banks must be designed, installed and maintained to minimise
the potential for stormwater runoff to enter areas disturbed by the activities.

E3 Sediment basin(s) must be installed and maintained to collect and treat stormwater runoff from all
disturbed areas of the approved place and areas in which any earthen material is stored.

E4 Any sediment basin(s) must be designed, constructed and maintained to contain the run-off expected
from a 24 hour storm event with an average recurrence interval of 1 in 10 years.

E5 Any sediment basin(s) must be operated in such a manner that within 5 days of the most recent rainfall
event, the required design capacity of the storage volume is available for capture and storage of
stormwater runoff from the next rainfall event.

E6 Contaminants other than settled or treated stormwater from the stormwater collection system must not
be released to any waters (including the bed or banks of any waters).

E7 Notwithstanding condition E6, settled or treated stormwater released must not have any properties nor
contain any organisms or contaminants in concentrations that are capable of causing environmental
harm.

E8 There must be no controlled discharge of contaminated site waters to any waters, roadside gutter or
stormwater drain other than in compliance with Table 1 — Water Quality Release Criteria.

E9 Extraction activities must be conducted in a manner that avoids disturbance of groundwater.

Table 1 — Water Quality Release Criteria

Quality Release Limit Monitoring Frequency

Characteristics

pH 6.5 -8.0 Prior to and daily during

discharge’
Total Suspended 50 mg/L Prior to and daily during
Solids discharge’

 

 

 

 

: Discharge waters are to be monitored within sediment basin(s) at the point of discharge.

 

Page 6 of 9» 120607 « Version 1

 

 

 

Department of Environment and Heritage Protection
Log in to download the original file

SPCE05212613 Permit.pdf · 1.0 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.