FINANCIAL PERFORMANCE REPORT - NOVEMBER 2025 · Report

of 9

Page text shows just the words. Original shows the document exactly as it was published.

GENERAL COMMITTEE MEETING                                                       15 DECEMBER 2025



Major capital grants and subsidies received to 30 November 2025 by project are outlined in the
following table.




Capital Expenditure
At 30 November 2025, actual capital expenditure (excluding commitments) was $15.6m or 16.3% of
Council's $95.8m capital works program. However, when this expenditure is adjusted to exclude
$4.6m of other capital expenses associated with the write off of assets, actual capital expenditure
was $11.0m or 11.5% of the revised capital budget against a target of 41.7%.

Of the total year to date capital expenditure, $2.5m relates to carry-over projects from 2024-25 with
a further $1.1m relating to unbudgeted works mainly associated with the purchase of 516 Upper
Pinbarren Road, with this acquisition funded from Council's Environmental Levy.

Detailed discussion of the progress of the capital works program is provided through a separate
quarterly report by the Infrastructure Team. In the next budget review, Council officers will look to
recast the 2025-26 capital works program to better reflect forecast actual and financial delivery at 30
June 2026.

Excluding loan redemption payments, donated assets and other capital expenses, the following table
outlines the progress of the capital works program by portfolio at 30 November 2025.
Log in to download the original file

Report.pdf · 721 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.