Stormwater Management Plan MCU17/0014
Original PDF page 7, section 1. The text section number identifies this passage in the reader.
BORNHORST + WARD | DOONELLA STREET UNITS
Queensland Urban Drainage Design Manual was used to identify the design storm events for this development
as:
Minor (piped flow) - 10% AEP (1 in 10 year ARI)
Major (overland flow) - 1.0% AEP (1 in 100 year ARI)
Flow rates for the developed site have been evaluated as a total discharge from the site.
4.1.1 Rainfall Data
The IFD data used in the Rational Method calculations was obtained from the Australian Bureau of
Meteorology website based on the approximate latitude and longitude of the development site (LAT
26°23'33.15"S, LONG 153° 2'16.94"E). This data indicated the 60 minute, 10 year ARI rainfall intensity
applicable to the development site is 72mm/hr. This rainfall intensity was used in conjunction with the fraction
impervious values to determine the coefficients of runoff for the existing and developed phases of the
development in accordance with QUDM.
4.1.2 Peak Flow Discharge
The coefficient of runoff was taken to be 0.76 and 0.86 for the existing and proposed scenarios respectively.
This was determined through investigation of the existing and proposed impervious areas.
The time of concentration for both cases was determined in accordance with QUDM. The existing time of
concentration for the site was calculated as 16.4 minutes based on a standard inlet time of 5 minutes from the
roof to ground, and 30m of overland sheet flow with a 6.7% gradient. This existing time of concentration was
evaluated from the residential building to the north of the site to the point of discharge situated in the
southeast corner of the site.
The developed time of concentration was adopted as 12 minutes based on a standard inlet time of 5 minutes
and approximately 2 minutes of pipe flow. The pipe flow travel time was determined using Figure 4.8 of QUDM
with a travel length and grade of 45m and 1% respectively, running along the eastern boundary of the site
towards the point of discharge situated in the southeast corner of the site.
The following table is a summary of the peak site stormwater discharges for varying storm events, calculated in
accordance with the Rational Method as outlined in the Queensland Urban Drainage Manual, to the southeast
corner of lot 32 Doonella Street for existing and developed conditions
Bornhorst + Ward Pty Ltd
Level 4, 67 Astor Terrace, Spring Hill, Qld 4000 Page 4
Ph. (07) 3013 4699 / [email protected]
A.B.N. 78 010 151 354
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Stormwater Management Plan MCU17_0014.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.