Appendix I - Stormwater Management Plan

Attached to the e-mail MCU14/0083 Appendices.

of 77

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
       1         Introduction

                 Projex Partners have been engaged by Mogpropmanagement Pty Ltd to prepare a
                 Stormwater Management Plan (SMP) to support a Material Change of Use
                 application for the proposed development at Lot 102 on SP241371 located at
                 Gateway Drive, Noosaville. The site is approximately 0.127 ha in area and is
                 proposed to be developed for a tyre retailer.
                 The object of this Stormwater Management Plan is to demonstrate how this
                 development will comply with Council’s stormwater management requirements. More
                 specifically the objectives are to demonstrate the following:
                            How stormwater will discharge to a lawful point of discharge;
                            How the impacts of stormwater run-off quality and quantity will be reduced.
                 This SMP has been prepared with consideration of the following documentation:
                      The Noosa Plan, Planning Scheme Policy 5- Engineering Design Standards-
                       Roads, Drainage and Earthworks;
                      Queensland Urban Drainage Manual (2013);
                      Music Modelling Guidelines Version 1.0 – 2010 (Water By Design, 2010);
                      Urban Stormwater Quality Planning Guidelines (Department of Environment
                       and Heritage Protection, 2010);
                      Institute of Engineers, Australia Soil Erosion and Sediment Control
                       Engineering Guidelines for Queensland Construction Sites;
                      Preliminary layout plans at Appendix A.




Mogpropmanagement Pty Ltd                            Page 1                                   205-002-002R
Stormwater Management Plan
Noosaville Site
Log in to download the original file

Appendix I - Stormwater Management Plan .pdf · 7.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.