Council archive · source document
Decision Notice - Change to an Existing Approval - 010.2006.00002232.001 [As Published] · 142006.2232.02
2006/2232
or as modified herein
15. Roof and surface runoff connection to Council’s kerb and channel and drainage system shall
be as shown on drawing No. 1470-0-2A (Construction Hydraulics). Kerb adaptors shall be
used in the kerb.
16. A Traffic Management Plan by a suitably qualified engineer RPEQ must be submitted to
Council prior to the pre start meeting. The Traffic Management Plan shall detail the following:-
a. The truck routes and manoeuvring on and off the site and what traffic controls are in
place. It must be remembered that delays to Gympie Terrace or Thomas Street general
traffic is not acceptable to Council.
b. The Gympie Terrace and Thomas Street footpaths shall remain open with the use of
barriers and or traffic controllers.
c. All construction staff should be provided with on site parking as the existing parking in
the Gympie Terrace/ Thomas Street Precinct is as capacity.
17. Fill imported to the site may only be from a site licensed with The Environment Protection
Agency or from a site for which a Development Permit for Operational Works has been issued
approving the export of fill. A soil report shall be submitted certifying that the material is free of
acid sulphate soils and other deleterious materials.
18. The full width footpath shall be continued across the frontage to the south of the access. The
footpath shall have a slip resistant surface. The alignment, of which, shall be determined on
site with Council’s Construction Technical Officer. The expansion joints in any
bikeway/footpath shall be “sawcut” not trowel jointed.
19. The pram ramp on Gympie Terrace frontage as required by Condition No. 36 of MCU
2005/1189 shall be determined on site with Council’s Construction Technical Officer.
20. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
installed into the first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each
rain event.
These devices are to remain in place during the civil works and construction phases of the
development.
The location and type of device to be installed shall be established at the “pre start” meeting
with Council’s Construction Technical Officer and shall be installed prior to the
commencement of any works.
21. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’
notice of intention to commence works to arrange a “pre start” meeting regarding the civil
works.
22. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any sub contractors also have the appropriate insurance and public liability
documentation.
23. Prior to the “pre start” meeting, the principal contractor must be provided with a copy
of Council’s signed approved drawings and conditions by the applicant.
24. Please provide one copy (A3 size) of the approved plans and a copy of the job specifications
for Council’s Construction Technical Officer.
25. The Consulting Engineers for the project shall be currently Registered Professional Engineers
of Queensland (RPEQ). The consulting engineers are responsible for arranging all
inspections, with Council’s Construction Technical Officer or nominated staff. Council’s
Construction Technical Officer shall provide an inspection form for signing off by the Engineer
Page 3 of 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2006.00002232.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 68 KB (small file)
- File type
No other editions are linked here.