Decision Notice - Change to an Existing Approval - 010.2006.00002232.001 [As Published] · 142006.2232.02
2006/2232
45. Notwithstanding that Council has checked the plans with due care, where it is found during
construction that variations exist with Council's standards, Council standards shall apply.
46. It is the responsibility of the applicant to ensure that its consultants and contractors take all
reasonable care during the construction of the engineering works to ensure that Council
property or facilities (such as underground drainage, water supply and sewerage) are
protected against any damage or interference whatsoever.
47. If any Council property or facilities should be damaged by the applicant or any of its
consultants or contractors through any cause whatsoever in the course of, directly or
indirectly, carrying out the engineering works, the applicant and/or its contractors shall
forthwith notify the Assessment Manager and shall forthwith rectify the damage to that
property or facility at its cost to the satisfaction of the Assessment Manager prior to the sealing
of the survey plan and/or acceptance of the works on-maintenance. Alternatively, the
applicant may request the Council to carry out the rectification work at the applicant's cost,
such cost being paid by the applicant to the Council prior to the sealing of the survey plan
and/or acceptance of the works 'on maintenance' provided that in the case of emergency, the
Council shall be entitled to rectify such damage at the cost of the applicant such cost being
paid prior to the sealing of the survey plan and/or acceptance of the work 'on maintenance'.
48. The Contractor shall make all necessary arrangements for supply of water required for
construction works. The use of hydrant standpipes on Council mains will NOT be permitted.
Contractors should contact Council’s Water Section on phone 5449 5254 to obtain an
application form for issue of a key to access Council’s water tanker filling stations. Conditions
of access and location of filling stations are detailed on the application form.
49. All signage, including that for safety during construction shall be in accordance with the
Manual of Uniform Traffic Control Devices and Main Roads Department Roadworks Signing
Guide.
50. As Constructed drawings in both hardcopy and digital format (ADAC) produced in GDA94
Zone 56 coordinate value to the standards and requirements of the Assessment Manager are
required for Council records. Such 'as constructed' drawings will be required prior to works
being accepted "on maintenance", where applicable. Requirements for "as constructed"
information are detailed in the current version of Council's Engineering Design Standards
(Water & Sewerage) Manual.
51. Release of plans of survey and/or acceptance of the works on-maintenance will not be
considered until lodgement of satisfactory 'as constructed' records.
Please note that bonding of outstanding works will not be considered by Council.
52. The Consulting Engineers for the project are responsible for arranging all inspections and
ensuring that all relevant details required by Council are supplied. The attached Water and
Sewerage Inspection Report form is to be kept by you and presented to Council's Inspector at
each stage of the development requiring a meeting or inspection. The Inspector will sign the
form at each stage when conditions have been satisfied. The works will be accepted 'on
maintenance' when this form, signed by the Inspector for each stage, is returned with a letter
requesting that it go 'on maintenance'.
53. It is Council policy that a maintenance bond be imposed on construction works during the
maintenance period. The maintenance bond shall be 5% of the agreed value of the
development obligations, or $1,500 whichever is the greater amount. This bond must be
lodged by (and shall only be accepted from) the Developer for the works.
54. Construction work and other associated activities are permitted only during the hours of
7:00am and 6:00pm Monday to Saturday. No work is permitted on Sundays or public
holidays, except where extended hours are approved by the Assessment Manager or his
nominee.
Page 6 of 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2006.00002232.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 68 KB (small file)
- File type
No other editions are linked here.