Decision Notice - Minor Change - Council Meeting Decision - 132001 210127 3 [As Published]
Erosion and Sediment Control
41. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required
to be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General
42. Any damage caused to any public utility during the course of construction shall be repaired
to Council’s standards and at no cost to Council.
43. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
44. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to
or from the site shall be covered to prevent materials including dust being windblown from
the vehicle.
Additional Conditions – 20 July 2023 (132001.210127.3)
When Conditions must be Complied With
45. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
46. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below and in conjunction with Condition 15 of this
approval.
Plan No. Rev. Plan/Document Name Date
1907NOO_ J Proposed Site Plan, prepared by Enrich 19/06/2023
Architecture
PD_A_002.0
1907NOO_ F Proposed Overall Ground Floor Plan, prepared by 19/06/2023
Enrich Architecture
PD_A_003.1
1907NOO_ F Proposed Ground Floor Plan, prepared by Enrich 19/06/2023
Architecture
PD_A_011
1907NOO_ F Proposed First Floor Plan, prepared by Enrich 19/06/2023
Architecture
PD_A_012
1907NOO_ A Proposed Acacia Wing Refurb., prepared by 19/06/2023
Enrich Architecture
PD_A_014
1907NOO_ F Site Sections and Elevations, prepared by Enrich 19/06/2023
Architecture
PD_A_250
1907NOO_ E Banksia Wing Elevations, prepared by Enrich 19/06/2023
Architecture
PD_A_310
Page 6 of 13
Document Set ID: 22515524
Version: 7, Version Date: 27/07/2023