Attached to the e-mail MCU15/0034 Development Application - Cover letter, Forms, Proposal plans & Planning Reports.
Figure 5.1: Proposed access (arrowed) looking south east
NBN Co considers the site access to be appropriate given the NBN Co facility will not be a
significant generator of traffic. Once operational, the facility should require once annual
maintenance visits, but would remain unattended at all other times. As the facility is expected to
generate minimal trips per year, it is anticipated that traffic interference will be negligible.
During the construction phase, it is planned that a truck will be used to deliver the equipment and
a crane will be used to lift most of the equipment into place. Any traffic impacts associated with
construction are expected to be of a short-term duration and are not anticipated to adversely
impact on the surrounding road network. In the unlikely event that road closure will be required,
NBN Co will apply to the relevant authorities for permission.
A total construction period of approximately ten weeks (including Civil works and network
integration and equipment commissioning) is anticipated. Construction activities will involve four
basic stages:
• Stage 1 (Week 1) – Site preparation works, including field testing, excavation and
construction of foundations;
• Stage 2 (Weeks 2, 3 and 4) – Construction of the monopole;
• Stage 3 (Weeks 5 and 6) – Construction of the equipment shelter and fences;
• Stage 4 (Weeks 7 – 10) – Installation of antennas and radio equipment, as well as
equipment testing.
5.1.4 Utility Service Details
A new point of power supply will be required to operate the proposed facility. As the power
supply route will cross the Powerlink easement (Easement A on RP136904), referral to Powerlink
NBN-4BBZ-4GYM-5132-Schreibers Page 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.