Original PDF page 15, section 1. The text section number identifies this passage in the reader.

A number of options are available to reduce this shortfall in water supply. The options available consist of:

       1. Increase supply by increasing runoff catchment area
       2. Decrease demand by supplying non-potable use from other sources; and
       3. Combinations of 1 and 2.

The connection of the communal dining hall roof area to supplement the catchment for village 1 would provide an
additional 3,200m2 for collecting rainwater inflow to offset demand. This will need to be piped up to 200m to
connect these catchments, however as shown in Figure 5-2, this results in there being enough rainwater stored for
4 months of the year. The remaining 5.2ML of water required to be imported to site via water tanker service across
the year.


BOM - Site ID 040908                           Jan         Feb          Mar          Apr          May          Jun           Jul         Aug          Sep          Oct          Nov          Dec
Average days/month                              31          28           31           30           31           30           31           31           30           31           30           31
Mean rainfall (mm) for years 1996 to 2022        146.4       162.6        176.7        128.6        126.2        100.6           58.2        26.4         29.2         82.1         78.3       133.0
Generated RO/month                        1,512,194.97 1,679,528.02 1,825,169.75 1,328,335.20 1,303,545.12 1,039,117.58 601,159.47    272,690.90   301,612.66 848,027.37 808,776.41 1,373,783.68
Demand/month                              1,537,600.00 1,388,800.00 1,537,600.00 1,488,000.00 1,537,600.00 1,488,000.00 1,537,600.00 1,537,600.00 1,488,000.00 1,537,600.00 1,488,000.00 1,537,600.00
Surplus/deficient                          -25,405.03 290,728.02 287,569.75 -159,664.80 -234,054.88 -448,882.42 -936,440.53 -1,264,909.10 -1,186,387.34 -689,572.63 -679,223.59 -163,816.32
Storage                                       0.00      290,728.02 578,297.76 418,632.96 184,578.07 -264,304.35             0.00         0.00         0.00         0.00         0.00         0.00
Surplus/deficient                          -25,405.03 290,728.02 578,297.76 418,632.96 184,578.07 -264,304.35 -936,440.53 -1,264,909.10 -1,186,387.34 -689,572.63 -679,223.59 -163,816.32

DWG ID                                            Area (m2)
Village 1                                          2372.19987
Village 2                                          3092.70257
Village 3                                          1630.98504
Communal dining hall                               3233.31311

                                                     10,329.20

No. EP                                                     160
Drinking water AD/ day                                    36.8
Non-drinking water AD/ day                                12.8
Water Demand (kL) / day                                   49.6


Figure 5-2 - Option 1 Water Supply and Demand


Option 2 would involve the utilisation of the large 100 Acre dam, which is currently used to irrigate the site as well
as several site bores that may potentially be used to supply non-potable water demands generated by the facility
to reduce the drawdown of the clean, captured roof run-off allowing it to be used principally for potable water
supply. Based on the SEQ Code and excluding non-potable water demands, the potable water demand per EP is
150L/day.

Option 2 has been modelled in Figure 5-3 using the following parameters:
   • Site occupancy of 80%: A 100% occupancy rate does not reflect the actual operation of the site with an
       80% occupancy rate considered more appropriate (i.e. average duration of persons utilising the site is
       approximately 5.5 days per week).
   • Communal dining is excluded: There is significant distance between this storage point and the villages end
       of line connection. Whilst this is a worthwhile option to consider as a redundancy in storage capacity, the
       modelling has been based on a gravity based potable water storage adjacent to the village.
   • Empty tanks: The tanks are assumed to be empty at the commencement of modelling.
BOM - Site ID 040908                          Jan            Feb            Mar          Apr          May            Jun             Jul           Aug            Sep             Oct           Nov           Dec
Average days/month                             31             28            31           30           31              30             31             31             30             31             30           31
Mean rainfall (mm) for years 1996 to 2022         146.4            162.6       176.7        128.6        126.2           100.6             58.2          26.4           29.2            82.1          78.3       133.0
Village 1                                                                                                                                                                                                                 Storage size
Generated RO/month                          347,290.06       385,719.70    419,167.72   305,064.90   299,371.62     238,643.31     138,062.03      62,626.08      69,268.24     194,757.61     185,743.25    315,502.58
Demand/month                                279,000.00       252,000.00    279,000.00   270,000.00   279,000.00     270,000.00     279,000.00     279,000.00     270,000.00     279,000.00     270,000.00    279,000.00
Surplus/deficient                            68,290.06       133,719.70    140,167.72    35,064.90    20,371.62 -    31,356.69 -   140,937.97 -   216,373.92 -   200,731.76 -    84,242.39 -    84,256.75     36,502.58      350 KL
Storage                                      68,290.06       202,009.76    342,177.48   350,000.00   350,000.00     318,643.31     177,705.34            -              -              -              -       36,502.58
Imported Water                                     -                -             -            -            -              -              -   -    38,668.58 -   200,731.76 -    84,242.39 -    84,256.75           -

Village 2                                                                                                                                                                                                                 Storage size
Generated RO/month                          452,771.66       502,873.44    546,480.54   397,721.55   390,299.06     311,125.88     179,995.29      81,647.35      90,306.91     253,910.88     242,158.61    411,329.44
Demand/month                                200,880.00       181,440.00    200,880.00   194,400.00   200,880.00     194,400.00     200,880.00     200,880.00     194,400.00     200,880.00     194,400.00    200,880.00
Surplus/deficient                           251,891.66       321,433.44    345,600.54   203,321.55   189,419.06     116,725.88 -    20,884.71 -   119,232.65 -   104,093.09      53,030.88      47,758.61    210,449.44      250 KL
Storage                                     250,000.00       250,000.00    250,000.00   250,000.00   250,000.00     250,000.00     229,115.29     109,882.64       5,789.55      58,820.43     106,579.04    210,449.44
Imported Water                                     -                -             -            -            -              -              -              -              -              -              -             -

Village 3                                                                                                                                                                                                                 Storage size
Generated RO/month                          238,776.21       265,198.17    288,195.06   209,744.68   205,830.31     164,077.10      94,923.33      43,058.01      47,624.76     133,903.87     127,706.13    216,921.01
Demand/month                                119,040.00       107,520.00    119,040.00   115,200.00   119,040.00     115,200.00     119,040.00     119,040.00     115,200.00     119,040.00     115,200.00    119,040.00
Surplus/deficient                           119,736.21       157,678.17    169,155.06    94,544.68    86,790.31      48,877.10 -    24,116.67 -    75,981.99 -    67,575.24      14,863.87      12,506.13     97,881.01      175 KL
Storage                                     119,736.21       175,000.00    175,000.00   175,000.00   175,000.00     175,000.00     150,883.33      74,901.33       7,326.10      22,189.97      34,696.10    132,577.11
Imported Water                                     -                -      169,155.06    94,544.68    86,790.31      48,877.10            -              -              -              -              -             -

Figure 5-3 - Option 2 Water Supply and Demand per Village

Project number 20220146                                                                                                                                                                           Page 15 of 20
File RECOR Stormwater Management Plan- 20220146.docx, 2022-09-06 Revision 0

P +61 7 5211 1003                                                   A 37 Mary St, Noosaville Qld 4566                              E [email protected]                                          recorconsulting.com
Log in to download the original file

Att8 - SWMP.pdf · 25.5 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.