Response to Information Request - 5 April 2018 · 132007.12.8
Attached to the e-mail 132007.12.8 - Response to Information Request.
“Adamson Town Planning, specialising in providing higher order town planning advice”
nor is it reasonable in the circumstances to require an easement over the relocated sewer
within the Telstra Depot land (Lot 5).
With respect to the further issues raised in the email of 17 January 2018, the following
comments are provided.
Issue
Specific outcome O1 requires that downstream properties are not adversely impacted by the
development.
Drawing 15652-SK1 shows the Bioretention basin will extend right up to the property boundary
with the invert level from the outlet pipe at RL4.7. Given that this is below the surface level of the
adjoining property, it is expected that the applicant is proposing to include scour protection as
well as stormwater infrastructure in the form of the outlet pipe within the adjoining property.
Info Required
Demonstrate that all infrastructure, including scour protection for the overflow weir along with
the low flow pipe will be able to be contained entirely within the applicant’s property.
With respect to the above, the following advice has been provided from TOD Consulting:
The sections X and Y on drawing 15652-SK1 are probably a little misleading with respect to the
existing ground levels. In reality the ground levels along the wall adjacent to the boundary vary
from RL 5.2 to RL 4.7. The level contours in the neighbouring property indicate that the existing
surface level adjacent to rock rubble dissipater is at or below RL 4.7. As shown on section X the
weir for the bio basin is located at the western end of the basin and discharges water onto the
rock rubble dissipater. Water for the rock rubble dissipater sheet flows into the neighbouring
property (park).
It is noted that the previous approval over the land for the multi-level carpark structure and
the subsequent operational works approval (Attachment 2) allowed for the construction of
the stormwater retention basin in the same location. The proposed retention basin is
essentially the same design as that previously approved.
Issue
Specific Outcome O8 of the Water Sensitive Design Code of the Noosa Plan requires that the
scale of the development provides adequate footprint to integrate all elements of the stormwater
quality treatment infrastructure including maintenance access without the need for retaining
walls.
Info Required
Demonstrate how the design of the proposed bioretention basin is consistent with the Water by
Design Bio-Retention Technical Design Guideline (the acceptable solution for Specific Outcome
O8) in terms of:
4|Page
14006 – Noosaville Medical and Professional Centre, New Office and Carpark Structure
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Information Request - 5 April 2018.pdfRelated documentApplication case desk ↗
About this file
- File size
- 257 KB (small file)
- File type
No other editions are linked here.