               30.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               31.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               32.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               33.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               34.    All fill and associated batters must be contained entirely within the subject site unless written
                      permission from the respective landowner(s) is provided to Council. All earthworks must be
                      undertaken in accordance with the provisions of Australian Standard AS3798: Guidelines on
                      Earthworks for Commercial and Residential Developments.
               35.    Where the development involves excavation or filling over, or adjacent to, drainage, water
                      supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
                      provide a freeboard of 100mm above the finished ground surface level.
               36.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               37.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.        Where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                                or
                      b.        where otherwise, upon completion of the works associated with the development.
               38.    Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval
                                                       OPERATIONAL WORKS
               APPROVED PLANS
               39.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                           Plan No.     Rev.   Plan/Document Name                                        Date

                           C020         .      Siteworks and Drainage Plan prepared by Empire 09/02/2021
                                               Engineering
                                               As annotated by Council

                           C040 A       .      Signs and Linemarking plan prepared by Empire 08/12/2020
                                               Enigneering

                           06           B      Landscape Plan, prepared by Building Suncoast Green -


                                                                                                        Page 5 of 14
Document Set ID: 22542722
Version: 4, Version Date: 16/08/2023

Used in these records

About this file

File size
194 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change - MCU21 0002 01 [As Published].pdf · 194 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.