Delegated Report - Code - Planning RAL23 0022 7 OPW23 0187 [As Published]
Damage to Services and Assets
45. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
Certification
46. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
5. REFERRAL AGENCIES
The referral agencies applicable to this application are:
Referral Status Referral Agency and Referral Trigger Response
Address
Concurrence SARA at DILGP SARA Schedule 10, Part 9, The agency provided its
at DILGP Via MyDAS2 Division 4, Subdivision 2, response on 25
at https://prod2.dev- Table 1 – Reconfiguring January 2024
assess.qld.gov.au/suite a lot within 25m of a (Reference No. 2312-
/ (for assistance, State transport corridor 38390 SRA). A copy of
contact DILGP at 5352 the response is
9701 or attached
email:[email protected]
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Building and Construction Industry (Portable Long Service Leave) Levy
2. The QLeave levy must be paid prior to commencing any works on site where required.
Private Infrastructure
3. All private infrastructure for the development must be designed to meet the planning scheme
requirements unless otherwise agreed by the relevant authority.
General Advisory Notes
4. As the driveways are private structures, the owner bears full responsibly for the standard of
its construction, maintenance and any liabilities associated with its construction.
Page 12 of 14
Document Set ID: 22849946
Version: 6, Version Date: 25/03/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.