               5.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               6.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               7.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance Inspections Request
               8.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days notice of preferred inspection time.
               9.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               10.    A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise.
                      Environmental Advisory Notes
               11.    The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               12.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               13.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               14.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                              If at the time of request for plan sealing, the method of short-term stabilisation has not
                              achieved a level of stability that Council's Officers believe will have a high probability
                              of achieving long term stability in determining whether the site is capable of achieving
                              medium to long-term stability:
                              •    evidence that the site has been effectively stabilised in the short term;
                              •    evidence that soil has been adequately ameliorated;

                                                                                                         Page 13 of 14

Document Set ID: 22849946
Version: 6, Version Date: 25/03/2024
Log in to download the original file

Delegated Report - Code - Planning RAL23 0022 7 OPW23 0187 [As Published].pdf · 5.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.