8. Engineering Report and Plans

of 61

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (11.3 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 10, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
The stormwater quality management objectives during the construction phase will be addressed in separate
Erosion and Sediment Control Plans (ESCP) prior to the commencement of works. The efficiency of the
Stormwater Quality Improvement Devices (SQIDs) will be modelled for efficiency and will consist of baskets
(SPEL Stormbaskets or similar) in the carpark gully inlets and bioretention systems in the landscaping design.
The proposed stormwater drainage for the development is shown in plans 188-002-400 to 402 as part of
Appendix A. These plans demonstrate the proposed drainage system discharging to the rear of the property
along with the drainage calculations and availability of landscaping area for the proposed bio-retention
systems.



           SEWER RETICULATION

An existing sewer main is located along the western boundary. A 150mm diameter (u-PVC) pipe traverses the
property from the north to the south and flows towards the southern pump station in Rufous Street. Being a
proposed commercial development, the sanitary drainage from the property will connect into the manhole in
the south-west east corner of the site.


The existing sewer infrastructure is shown on the Assets map provided in Appendix C.
The proposed sewer drainage for the development is shown in plans 188-002-601 as part of Appendix A. These
plans demonstrate the proposed connection point of the sewer into the existing manhole.



           WATER RETICULATION

An existing AC 100mm diameter main is located within the David Low Way road frontage on the eastern
boundary. The proposed connection will include a fire hydrant and water meter assembly in accordance with
the relevant plumbing code and hydraulic plans.


The proposed water connection for the development is shown in plans 188-002-501 and 502 as part of
Appendix A. These plans demonstrate the proposed connection point of the water and the proposed detail of
the system (subject to hydraulic design)


The existing water infrastructure is shown on the assets map provided in Appendix C.




                                              Page 10 of 13
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092           [email protected]
Log in to download the original file

8. Engineering Report and Plans.pdf · 11.3 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.