24-7-19 Attachment F Rev Stormwater Mgmt Plan

of 34

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (22.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
18 July 2019



5         STORMWATER
5.1       Flooding

Based on Noosa Shire Council flood mapping, the site is not subject to flooding from any sources.


5.2       Site Based Stormwater Management Plan

The aim of the Stormwater Management Plan outlined below is to:

          Prevent or minimise adverse social or environmental impacts from stormwater runoff
           originating from the proposed development.
          Achieve acceptable levels of stormwater runoff quality and quantity.

The Stormwater Management Plan aims to identify Stormwater Quantity and Quality Best
Management Practice for the site and demonstrate that water quantity and quality impacts will be
minimised in receiving waters.

The Stormwater Management Plan outlines the site in two sections, the operational phase and the
construction phase. The operational phase addresses treatment of contaminated runoff from the
developed site by natural methods before discharging into receiving waters whilst the construction
phase of the Stormwater Management Plan addresses erosion and sediment control to prevent
contamination of water sources by stormwater runoff during construction of the site.


5.3       Operational Phase

5.3.1 Proposed Site Drainage

Stormwater runoff from the proposed development will be collected and conveyed in a new
stormwater pit and pipe network.

The new building and carparks will be constructed over a basement car park. The stormwater from
the roof and suspended car park will be directed to a new combined bioretention/detention basin
located along the Northern boundary of the site. Detained and treated water from the combined
bioretention/detention basin will discharge to an additional detention tank located under the drop
off area at the front of the building.

Stormwater runoff from the landscape areas at the front of the site will be conveyed along grassed
swales and discharge to the detention tank, via the new pit and pipe network.

Runoff from the courtyard area at the centre of the site will be collected and conveyed in the new
internal pit and pipe network to the detention tank.

Stormwater runoff from the car park access driveway at the South East corner of the site will
bypass treatment and detention and connect to the stormwater infrastructure constructed as part
of the masterplan ROL development.




Excellence with Economy in Engineering                                                               8
l:\7000-7999\7700-7799\7700\reports\18-07-19 stormwater management plan_issue d.docx
Log in to download the original file

24-7-19 Attachment F Rev Stormwater Mgmt Plan.pdf · 22.6 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.