Attachment 13- Amended Flood Study MCU12/0208
Very large file (37.1 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Original PDF page 33, section 1. The text section number identifies this passage in the reader.
Noosa on Weyba
Flood Study
It is noted that the Noosa Council Strategic Plan (1995) states that: “filling of areas other than the designated
Urban Area is not acceptable. Therefore, rural township development and rural residential development
which occurs beyond the Urban Area should not involve filling of the floodplain”. The filling proposed within
Lot 11 is located within the previous Maroochy Shire Council and therefore is not covered by the Noosa
Council Strategic Plan. In addition, the Noosa River flood modelling that was conducted in Mike 11, which
was used to inform the Strategic Plan, did not include Keyser Creek or Eenie Creek as flood storage and the
model sections did not extend across Lot 11.
The Sunshine Coast Regional Council Growth Management Position Paper (SCRC 2008) states that “new
urban development is avoided in flood prone areas and floodplains unless there is compelling justification
that demonstrates overriding community benefits and that any negative impacts resulting from development
can be appropriately and sustainably managed.” The question of whether this proposed development can
constitute an overriding community benefit is beyond the scope of this report. This report determines
whether there are any negative impacts in relation to local and regional flooding as a result of this
development.
9.2 Flood Impact of Cumulative Filling
th
Item 88 of the SCRC RFI (28 of February 2013) stated that:
“With respect to loss of floodplain storage it is stated in the Flood Study that the loss of flood storage is minor
when compared to the surrounding floodplain and Lake Weyba. The cumulative impact of all sites within the
Noosa River and Lake Weyba floodplain being developed with a loss of floodplain storage has however not
been considered. In such a large catchment area it is the cumulative impact rather than site specific impact
of lost floodplain storage which is of concern.”
An analysis was therefore conducted to look at the potential impact of additional filling on regional flood
levels. The analysis was limited to the extents of the flood model area and included filling of residential,
limited development and rural use areas that have been predominantly cleared (similar to the area of filling
proposed on site) and that are located in the 100 year ARI flood inundation extent. The existing Noosa
Airport and sportsgrounds on Weyba Road were also filled. The 100 year ARI flood inundation extent was
taken from SCRC mapping. The extent of filling assumed in the analysis is shown in Appendix I. The total
area of fill equalled 54.0 hectares, and the volume of fill required to provide 100 year ARI flood immunity was
3
estimated at 370,000m . This is over 14 times the volume of fill proposed for the site. The flood model was
modified by filling the 1D cross-sections where appropriate.
The intent of this analysis is to look at the impact of filling on regional flood levels, which are higher than the
local flood levels in the downstream sections of Noosa River, Weyba Creek and around Lake Weyba. It is
not intended to be used to justify uncontrolled filling of the floodplain areas, as even though the impacts on
regional flood levels may be negligible it is likely that filling would result in local flood impacts for surrounding
areas. More detailed flood modelling, similar to that conducted for this assessment, would be required to
determine local flood impacts. The volume of fill modelled for this scenario is therefore a worst case
scenario and is not representative of the volume of fill that would actually be possible. The results of the
regional cumulative flood impact assessment are shown in Table 9-2. The results show that the peak water
levels within Lake Weyba and Weyba Creek increase by up to 5mm, which is considered negligible. There
was also negligible impact within the 2D sections of the model.
Table 9-2 Cumulative Flood Impact
Cross-section 100 Year ARI Regional Difference
Peak Flood Level (m)
(mAHD)
Existing Case Proposed With Regional Proposed With Regional
Development Filling Development Filling
Only Only
Weyba 0.0 2.07 2.07 2.08 0.000 0.005
Weyba 1.0 2.07 2.07 2.08 0.000 0.005
Weyba 2.0 2.07 2.07 2.08 0.000 0.005
Weyba 3.0 2.07 2.07 2.08 0.000 0.005
Northbrook Corporation Pty Ltd Version 4 16 September 2013
Flood Study v4 2.doc Commercial in Confidence Page 28
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 13- Amended Flood Study MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 37.1 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.