CONFIRMATION OF MINUTES ORDINARY MEETING 20 AUGUST 2026 · 2026-08-20 Ordinary Meeting Minutes
ORDINARY MEETING | 20 AUGUST 2026
Council appreciates you raising this information regarding dog exercise arrangements
at Beach Access 37 and recognises that there are likely to be a range of community
views on this matter. These views include support for maintaining existing
arrangements, as well as proposals to expand or modify off-leash access. Any
changes to designated dog exercise areas would require careful consideration of
community feedback, environmental impacts, public safety, accessibility and
legislative requirements. Council intends to consider community feedback on dog
exercise areas as part of a future review of its Local Laws. The Local Law review
process is proposed to be considered through future budget deliberations, with the
next opportunity likely to be through the 2027-28 budget process. Should Council
resolve to proceed with a review, it will be undertaken in accordance with the State
Government's prescribed framework and will include formal community consultation
before any changes are determined.
8.3 PAT SPICER
Question 1:
As the 24/25 financial year is now history, for what was the $3.3 million
allocated in the 24/25 Noosa Council Budget for 62/64 Lake Macdonald Drive
project?
Response from Kim Rawlings, Director Strategy & Environment
The allocated $3.3 million was a high level initial construction cost estimate to
allow the project to proceed to the next stages. The project was delayed to
enable further community consultation resulting in design changes which
deferred construction until the 2025/26 financial year.
Question 2:
How much of that $3.3 million 24/25 financial year budget allocation for 62/64
Lake Macdonald Drive project was used?
Response from Kim Rawlings, Director Strategy & Environment
Of the total $3.3 million project budget, approximately $49,000 was expended
in the 2024/25 financial year, comprising staff time, consultation and design
costs. No remediation or civil work costs were incurred during this period, as
construction did not commence until the 2025/26 financial year.
The meeting adjourned at 10.25am
The meeting resumed at 10.40am
9 MAYORAL MINUTES
Nil.
Page 5 of 15