4. CONSTRUCTION PHASE MANAGEMENT
Erosion and Sediment Control
The management of the site during the construction phase is an important step in ensuring
water quality standards are achieved. Implementation of best practice Erosion and
Sediment Control techniques is imperative to managing the quality of runoff affected by
construction works.
The following points provide general guidance on the management of stormwater during
the construction phase. Detailed Erosion and Sediment Control Management Plans should
be developed in conjunction with the Operational Works design prior to construction works
commencing in accordance with the International Erosion Control Association (IECA) - “Best
Practice Erosion and Sediment Control (BPESC) document” and overseen by a Certified
Professional in Erosion and Sediment Control (CPESC) or Registered Professional Engineer
Queensland (RPEQ).
1. Establish a single stabilised entry/exit point for the site works;
2. Construct a shake-down grid at the entrance to facilitate the removal of sediment from
trucks leaving the site. The access road extending from the end of existing road or kerb
to the grid should comprise a 150-200mm deep pad of 40mm crushed rock;
3. Install sediment fences along the lower boundaries of the site;
4. Construct one or more strategically placed sediment basins in the proposed drainage
reserve and construct contour drains / bunds to direct disturbed runoff to the sediment
basins;
5. Install bins and/or wind-proof litter areas on-site to minimise the dispersion of gross
pollutants;
6. Maintain on site sufficient materials necessary for the emergency repair of all erosion
control devices. This includes silt fences, clean crushed rock for reapplication to the
entrance road and for replacement of rock within temporary drainage channels, and
flocculants for settling sediment basins;
7. Following each day’s construction works, ensure that any material on road surfaces is
swept from the road, and not permitted to be washed down the gutters and piped
drainage systems;
8. Quality of pooled water within sediment basins are to be monitored prior to
dewatering, sufficient time should be given to allow sediment to settle (possible with
the assistance of a suitable flocculent if necessary) &/or filtering during pumping
operations; and
9. Final establishment of bioretention basin should not occur until full stabilisation of
upstream catchment has occurred; preferably these should be temporarily turfed
during the maintenance period while dwelling construction is occurring.
It shall be the responsibility of the developer, through their principal contractor, to ensure that
temporary sediment and erosion controls are installed and maintained correctly.
21-0166SMP01-V1 | Stormwater Management Plan | 25 Pavilion Street, Pomona | 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.