84. The ground water in the monitoring wells must be tested for petroleum contaminants
immediately after either:
a. the discovery whether by routine test or otherwise that ground water may be
contaminated by petroleum originating from the property
b. the discovery whether pursuant to the loss monitoring procedure for the system
or otherwise that the system has a leak
c. when requested by Council
De-commissioning of the UPSS
85. Where more than 2 years lapses since a tank were decommissioned, the UPSS must
be permanently removed in accordance with the relevant Australian Standards and
Workplace Health and Safety Qld requirements.
86. Certification must be provided to Council confirming the UPSS de-commissioning
was conducted by a suitably qualified and experienced person, and that removal,
transportation and disposal was in accordance with the Standards and legislation.
87. At the time of abandonment of any UPSS the site must be investigated for
contamination. An assessment report must be prepared by a suitably qualified and
experienced person ( as required under the Environmental Protection Act 1994) to
verify the site has either met remediation criteria or is suitable for continued and
future use. The assessment report must be submitted to Council no later than 60
days of either the:
a. decommissioning of an UPSS if no soil or ground water remediation is required
b. completion of any remediation associated with the decommissioning of an
UPSS if remediation is required.
88. All records associated with the decommissioning of UPSS must be maintained for a
period of 7 years after removal of the UPSS. These records must be provided to
future owners/operators of the service station and property, as part of ensuring all
practicable measures have been implemented to prevent site contamination.
Noise
89. Mechanical plant and equipment, a/c units, motors, refrigeration equipment,
compressors, pumps etc. on site must be located within the building or suitably
provided with noise reduction measures and located to prevent a noise nuisance
beyond the boundary of the site and to not exceed the levels specified in Table 1.
Table 1
NOISE LIMITS AT A SENSITIVE RECEPTOR
PERIOD Noise level at noise sensitive place measured as the adjusted
maximum sound pressure level (Lamax, adj,T)
7am – 6pm Background noise level (LAbg,T) plus 5 dB(A)
6pm – 10pm Background noise level plus 5 dB(A)
10pm – 7am Inaudible
NOISE LEVELS AT COMMERCIAL PLACE
PERIOD Noise level at a commercial place measured as the adjusted
maximum sound pressure level (Lamax, adj,T)
7am – 6pm Background noise level (LAbg,T) plus 10 dB(A)
6pm – 10pm Background noise level plus10 dB(A)
10pm – 7am Background noise level plus 8 dB(A)
90. When requested by Council, a Noise Impact Assessment Report (NIAR) showing
monitoring and recording of noise levels must be undertaken to investigate any
complaint (other than a frivolous or vexatious complaint) caused by noise emissions
from operations at the premises.
Page 17 of 70
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.