Decision Notice - 010.2009.00000512.001 [As Published] · 132009.512
2009/512
dwg.3 First Level Floor Plan – Macchia Pty Ltd 8 July 2008
dwg.4 West Elevation – Macchia Pty Ltd 30 September
2008
dwg.5 North Elevation – Macchia Pty Ltd 11 November
2008
dwg.6 East Elevation – Macchia Pty Ltd 11 November
2008
dwg.7 South Elevation – Macchia Pty Ltd 11 November
2008
dwg.8 Section A-A – Macchia Pty Ltd 30 September
2008
dwg.9 Section B-B – Macchia Pty Ltd 11 November
2008
and as may be amended by these conditions and annotations on the plans
2. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
3. Earthworks required on site shall be carried out in accordance with Council’s Planning
Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or concentrate or direct overland flow onto an
adjoining property.
4. The beam and associated roof structure to the southern side of the garage shall be removed
from within the front setback.
5. The building height and the privacy screen to the north side of the dwelling shall not exceed
8.0 metres above the natural ground level and the finished ground level.
6. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council at completion of work confirming compliance with the
maximum allowable building height as required by either the conditions of approval or the
Planning Scheme.
7. One native 45-litre street tree shall be planted to the road reserve in accordance with Council’s
Landscaping Guidelines.
8. All vegetation retained shall be protected from interference resulting from clearing or
construction activities by:
8.1 Clearly marking vegetation to be retained with flagging tape;
8.2 Installing protective fencing around the drip line of the vegetation;
8.3 Stockpiling, storage and vehicle parking occurs in already cleared areas and does not
cause interference with vegetation; and
8.4 Low impact construction techniques are used around vegetation to minimise
interference with the vegetation.
9. Cleared vegetation is to be suitably processed by one of the following methods and removed
from the site:-
9.1 Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
minimum of 10 metres between edges of heaps.
Page 2 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2009.00000512.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 62 KB (small file)
- File type
No other editions are linked here.