                      *(Refer to Advisory Note)
                      Revegetation of the coastal setback
               29.    Prior to the commencement of use the applicant shall undertake revegetation of the coastal
                      setback. The revegetation, shall be 5.0 metres in width from the seaward or rear boundary
                      of the site and shall include a mix of native landscaping such as ground covers, shrubs and
                      trees to provide adequate landscape buffering to protect the coastal dune system.
                      Plantings are sourced from the Noosa Plan 2020 - PSP2 Landscaping planning scheme
                      policy and maintained for the life of the use at the site.
                      (* Refer to Advisory Note)
               30.    Where damage occurs to any Council asset as a result of the development works, it must be
                      repaired immediately where it creates a hazard that presents risk to person or property. Other
                      damage must be repaired prior to completion of works.
                      Retention of Existing Trees
               31.    Existing trees in the road reserve must be assessed by a qualified person* and retained and
                      protected where possible. Where mature trees are to be removed, reasonable grounds must
                      be given by the qualified person*.


               DEMOLITION WORKS
               32.    Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
                      solutions as contained in the Waste Management Code and Water Quality and Drainage
                      Code of the Noosa Plan 2020.
                      Works
               33.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste Management
               34.    Adequate area must be provided on-site for the collection and separate storage of recyclable,
                      non-recyclable, vegetative and hazardous materials in their specific waste streams during
                      removal or demolition works.
               35.    All waste materials must be removed from the site to avoid causing unhealthy conditions,
                      with the site left clean, tidy and free from any debris.
               36.    Where a development permit has not been issued for the future use of the site, hard surfaced
                      areas including concrete slabs must be removed and disturbed areas must be revegetated
                      in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
                      be turfed within 20 business days of completing the removal or demolition work. Health and
                      Safety
               37.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.
               38.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               39.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.


                                                                                                     Page 29 of 33

Document Set ID: 23561450
Version: 5, Version Date: 10/04/2025

Used in these records

About this file

File size
12.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU24 0094 [As Published].pdf · 12.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.