40. All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008. Note: Asbestos is a Regulated Waste. The Department of Environment &
Science licenses businesses that transport asbestos waste, and landfills that accept this
waste.
General
41. Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
protected from damage and made safe to the standard required by the regulatory authority.
42. Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
pre-existing conditions.
Plumbing and Drainage
43. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed water tight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
MNA_205215_33 00 33 ROSS CRESCENT, SUNSHINE BEACH 22 January 2025
Ross Crescent
Coastal Hazard Assessment prepared by
Sunshine Beach
Moffatt and Nichol
24096-001 0 Geotechnical Investigation prepared by 18 June 2024
Tectonic Geotechnical & Environmental
Engineers
S24-043 Stormwater Management Report prepared by 3 July 2024
Westera Partners
S24-043 Letter titled Response to Council’s Request for 4 September 2024
Information prepared by Westera Partners
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Page 30 of 33
Document Set ID: 23561450
Version: 5, Version Date: 10/04/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU24 0094 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 12.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.