2021-01-21 Ordinary Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
ORDINARY MEETING AGENDA 21 JANUARY 2021
9 ORDINARY MEETING REPORTS
1. T000018 PEREGIAN BEACH COMMUNITY HOUSE AND GREENSPACE
CONTRACT AWARD
Author: Director Community Services, Kerri Contini
Index ECM/ 46.02 - Council Owned Buildings / Properties
ECM/ Project and Contract/ T000018
Attachments 1. Design images
2. T000018 Evaluation Workbook
EXECUTIVE SUMMARY
This report provides a recommendation for the tender award to the preferred contractor for the
construction of the Peregian Beach community house, carpark and greenspace works.
RECOMMENDATION
That Council note the report by the Director Community Services to the Ordinary Meeting dated
21 January 2021 and award tender T000018 – for the construction of the Peregian Beach
Community House and Greenspace to Kane Constructions (Qld) Pty Ltd.
REPORT
1. Background
Between August and October 2018, Council received a combined $2.7 million of grant funding
from the Federal Government under the ‘Building Better Regions’ and the State Government
under the ‘Maturing the Infrastructure Pipeline Program’ to construct the third stage of the
Rufous Street Masterplan, which includes the two major elements of the new Peregian Beach
Community House and repurposing the existing community house to expand the Digital Hub.
To date the redevelopment of the Rufous Street precinct has consisted of the following stages:
Stage Description Year Status Cost
1 Land purchase and site 2014-15 Completed $1M
preparations
2 Masterplan for the Rufous St 2016-18 Completed $4M
precinct, design and
construction of Rufous Street,
Digital Hub and car parking
3 Planning, Design and 2019-22 Community House & $5.2M
construction of New community Greenspace -
house, Digital Hub expansion, Procurement (This report)
additional car parking and Digital Hub expansion -
greenspace Design phase.
Carpark - completed
Total $10.2M
Once all of Stage 3 is constructed, a total $10.2M of Council, State and Federal Government
funding will have been invested into the Rufous Street precinct.
Council previously tendered the project as a design and construct project as “RUFOUS
STREET COMMUNITY HOUSE (STAGE 3) AND CAR PARK, CONTRACT NO. 1819T084”
Page 11 of 26
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.