2021-01-21 Ordinary Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
ORDINARY MEETING AGENDA 21 JANUARY 2021
and following Council’s Ordinary Meeting dated 17 October 2019, executed the contract with
Peregian based contractor Ri-con Contractors on 28 October 2019.
On 20 January 2020, Council was advised without prior notice that Ri-con Contractors had
gone into liquidation. At this point the carpark was complete and the community house design
had commenced but was not complete. To enable the project to proceed, Council procured
the necessary design services to complete the designs and specifications and prepared a
traditional construct only tender.
2. Design
The design of Stage 3 is generally in accordance with the Rufous Street Masterplan, Material
Change of Use (MCU) approval MCU16/0044.01 and REC16/0009 and prepared in
consultation with the Peregian Beach Community House committee and Rufous Street Project
Control Group.
Specifically, the new community house design was developed to provide enduring, adaptable
and complementary community facilities that are suitable to the Peregian Beach location,
minimise energy use, and be in keeping with the Noosa Design Principles.
The community house scope includes:
130m2 Hall
40m2 Hire room
35m2 Meeting room
Office & reception
Under croft carpark – 23 spaces
Rooms for hire
Kitchen
Storerooms
Lift access
Landscaping
The Greenspace scope includes:
4000m2 of sculptured gardens
Playground
Footpaths
Turfed areas
Refer Attachment 1 – Design images.
3. Tender process
Council prepared and called for public tenders in accordance with the Local Government Act
2009. Tender T000018 was released via Vendor Panel on 19 August 2020, and also advertised
in Noosa Today on 21 August 2020 and online with Noosa News from 20 August 2020. The
tender closed on 22 September 2020 with four compliant submissions received.
4. Tender Assessment
The tender evaluation panel undertook an assessment of the following conforming tender
submissions, which are listed in alphabetical order:
Kane Construction (QLD) Pty Ltd
Midson Constructions (QLD) Pty Ltd
Murphy Builders Qld Pty Ltd
WAC & Co Pty Ltd
Two additional submissions were received and assessed as non-conforming and were not
considered.
The conforming tenderers were evaluated using the following criteria and weightings:
Page 12 of 26
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.