Roof Water & Stormwater Drainage
31.   Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
      (minimum storage 3000 litres per attached dwelling unit) that is installed to ensure water from
      the tank is used for external uses (such as watering gardens, irrigation, ornamental ponds,
      water features, topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of
      toilets internal to the dwelling. All rainwater tanks are to be designed and installed in
      accordance with the Queensland Development Code (QDC), and shall be part of the plumbing
      application in conjunction with the building approval. The location and capacity of the tanks
      shall be clearly shown on the plans submitted for Operational Works approval and any
      overflow shall be directed to the.
32.   All stormwater drainage (including roof water overflow from the rainwater storage system)
      shall be collected and discharged so there is no net increase in stormwater runoff from the
      site. Stormwater drainage permitted to drain from the site shall be discharged to Council’s
      kerb & channel street drainage system in Edward Street. Plans of the drainage design shall
      be prepared by a Registered Professional Civil Engineer and submitted to Council prior to
      obtaining a Development Permit for Operational Works.
      The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
      drainage system at any one location is 25 litres/second.
33.   As the site is proposed to be filled, appropriate stormwater drainage pipes shall be installed
      within the site to collect and discharge stormwater runoff from all adjoining properties to
      prevent additional ponding/flooding on these properties.
34.   Drainage of the site shall be in accordance with the principles of Council’s - Noosaville Master
      Drainage Plan to ensure that the site discharges to the appropriate drainage catchments. This
      information can be obtained from Council’s Technical Officer - Development, by contacting
      5449 5263.
35.   All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
36.   The site shall be connected to Council’s existing sewerage reticulation systems and be
      constructed in accordance with Council’s standards and requirements at no cost to Council.
37.   The existing sewer main that is located in the adjoining property at the rear of the site and the
      ‘zone of influence’ (taken as the area within a 45-degree angle measured from the invert of the
      sewer main to the finished surface level) shall be accurately located and determined by a
      licensed Surveyor and shown on all plans submitted for Operational Works approval.
      To ensure Council’s sewer main is accessible for maintenance purposes and is protected from
      risk of damage no structures requiring a building permit (eg. swimming pools, retaining walls
      exceeding 1m in height, raised terraces, etc) shall be constructed within this ‘zone of influence’
      or within 1.5m of the centreline of the sewer main, whichever is the greater. As such the
      applicant shall amend Operational Works plans including Building plans to ensure compliance.
Town Water Supply
38.   The site shall be connected to Council’s existing town water supply and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.
39.   Each individual water connection to the water reticulation system shall extend to the property
      boundary and be metered. All fees for the supply of water meters shall be paid to the Council.
40.   All water meters must be located outside the property boundary and in an easily assessable
      location to facilitate unhindered reading by Council and/or Council’s contracted water meter
      readers, and not behind fences or locked gates. In this regard approval of the water meter
      configuration and location must be obtained from Council’s Water & Sewerage Capital Works
      Manager prior to lodgement and approval of hydraulic drawings.

                                                                                          5 of 14

Used in these records

About this file

File size
82 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - 010.2008.00000110.001 [As Published].pdf · 82 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.