Negotiated Decision Notice - 010.2008.00000110.001 [As Published] · 132008.110

of 14

Text shows just the words. Original shows the document exactly as it was published.

                                                                                       2008/110



Erosion and Sediment Control
46.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to
      be submitted to the Council for approval prior to obtaining a Development Permit for
      Operational Works.
Contributions Towards Council Infrastructure
47.   Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
      upgrading various infrastructure at the rates applicable at the time of payment. An estimate
      only of the contribution amounts under the current Council policies and requirements is
      outlined in the table below:

       Contribution Required For:                                                   Amount:

       PSP12 – Public Open Space Contributions (Park)                               $3,074

       PSP16 – Sewerage Headworks Contributions                                     $3,444

       PSP17 – Water Supply Headworks Contributions                                 $3,130

       PSP20 – Pathway Trunk Network Contributions                                  $691

       Stormwater Drainage Contributions in accordance with the Noosaville /        $4,927
       Ward Park Tewantin Master Drainage Plan

       TOTAL Contribution Amount =                                                  $15,266

       Please note, that these amounts are all subject to variations in the Consumer Price Index, All
       Groups Brisbane from March 2008 until the date of payment.

      All contributions must be paid prior to the issue of a Development Permit for Operational
      Works.

Environmental Health
48.   Where the development involves the removal, relocation or demolition of a building, a Waste
      Management Plan (construction and demolition) shall be submitted prior to demolition,
      removal or relocation of any building other than a shed.
      Waste Management Plans (construction and demolition) are required to be submitted in
      accordance with Planning Scheme Policy 11, Waste Management Plans see table below.
      Waste storage areas are to provide for adequate separation of all reusable, recyclable and
      waste materials. These shall be located so that they are convenient and safe to use. (Refer to
      Noosa Council Waste Management Code)

      The Plan shall contain the following information:
      1.        The site area for the storage and separation of waste is to be shown on the plan
                drawings accompanying the application.
      2.        A waste management table as indicated below is to be completed showing how
                waste material is to be segregated - recycled – reused or disposed.



                                                                                        7 of 14

Used in these records

About this file

File size
82 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - 010.2008.00000110.001 [As Published].pdf · 82 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.