PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 9 FEBRUARY 2021
d) No incorporation of artificial grass; and
e) Detail of the front interface of the retaining structures to the path along Noosa
Drive, including any location of any above ground services.
26. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
Retention of Existing Trees
27. Trees identified for retention, as shown on the Tree SRZ Layout Plan, Drawing No. P07,
Issue A, prepared by 360 Civil Consulting and dated September 2020, must be retained.
28. All works must be carried out generally in accordance with section Tree Protection
Methodology of the Arboricultural Report and Tree Protection Methodology / Plan report
listed within this Decision Notice, with the following amendments incorporated into the
document:
a) Inclusion of a plan clearly numbering the trees in accordance with Tree SRZ Layout
Plan, Drawing No. P07, Issue A, prepared by 360 Civil Consulting and dated
September 2020;
b) Details of the construction methodologies and tree protection measures to be
engaged during the construction of the retaining walls and stairway to the south
eastern portion of the lot;
c) Details of the constructions methodologies to be engaged for the laying of the water
detention cells in the tree protection zones;
d) Details of the construction methodologies to be engaged for the decommissioning
of the retaining wall and re-landscaping to the frontage around the Melaleuca; and
e) Details of the methods to be engaged during the demolition of the existing
development.
29. The report as referenced in Condition 28, must be resubmitted to Council incorporating
the above amendments prior to the issue of any Development Permit for Operational
Works or Permit for Demolition Works.
External Works
30. Noosa Drive must be upgraded for the length of its frontage to the subject site. The
works must be undertaken in accordance with an Operational Works approval and must
include the upgrade of the existing footpath for site’s frontage to Noosa Drive for the full
width between the kerb and the front boundary of the site. The pathway must be
constructed with granite pavers to match existing granite pavers in the general vicinity of
the site (Hastings St/Noosa Drive).
This condition is imposed pursuant to s128 of the Planning Act 2016 being necessary
trunk infrastructure identified by Council’s LGIP to service the development.
Stormwater Drainage
31. Stormwater runoff from the development must be disposed of on-site without causing
scour or damage to the subject site or any adjoining property. The works must be
undertaken in accordance with an Operational Works approval and be generally in
accordance with drawing number P06 prepared by 360 Civil Consulting dated September
2020.
Page 8 of 98
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.