SUPERSEDED Decision Notice OPW25 0042 · OPW25/0042
ii. A waste collection/haulage conflict management plan prepared in collaboration
with Noosa Council’s Waste Team identifying waste collection times and haulage
schedules designed to avoid traffic conflicts.
iii. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction.
iv. Restricting on-street car parking to facilitate safe turning widths for HV’s. (*)
(*) Refer to Advisory Note
v. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased.
vi. Proposed fencing to the site during the construction phase of the development.
e. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures.
f. Works programme identifying key components of the works and their respective
durations.
g. Establishment of a communication protocol including an on onsite public information
session, and correspondence to adjoining owners, emergency services and local
businesses to advise of agreed construction times, impacts on traffic and services and
other relevant issues.
h. Include a post out to the local residents and businesses, including all the residents
along the haulage route up to Reef-Eenie Creek roundabout advising of the proposed
development including the expected time frames and the site contact details.
i. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
j. identification of complaint management procedures including:
i. contact details for the on-site manager.
ii. dispute resolution procedures.
k. details on the location of external fill/dump sites/sources, the haulage route, type of
vehicle to be utilised during filling operations and frequency of usage. Note any
damage to the existing road system as a result of haulage operations shall be fully
repaired at the applicant’s expense.
12. All works must be carried out in accordance with a site specific Geotechnical Report prepared
by a qualified person* and endorsed prior to a prestart meeting.
*(Refer to Advisory Note)
13. Prior to the commencement of municipal works associated with this development, Council
requires the provision of a bank guarantee, or a cash bond, of not less than 10% (minimum
of $5000) of the value of the municipal works.
14. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
15. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
16. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
Page 5 of 15
Document Set ID: 24023937
Version: 2, Version Date: 12/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice OPW25 0042.pdfRelated documentApplication case desk ↗
About this file
- File size
- 192 KB (small file)
- File type
No other editions are linked here.