Decision Notice - 010.2008.00000425.001 [As Published] · 142008.425

of 7

Text shows just the words. Original shows the document exactly as it was published.

                                             Officer:          Ronald Read
                                             Direct Telephone: (07) 5449 5263
                                             Response Address: PO Box 141, Tewantin QLD 4565
                                             Email:            [email protected]
                                             Our Reference:    2008/425
                                             Your Reference:
9 May 2008

Ken Hicks & Associates Pty Ltd
PO Box 6380
MAROOCHYDORE BC QLD 4558




Dear Sir/Madam,

                                      Decision Notice
                                 Integrated Planning Act 1997
I refer to your application and advise that on 9 May 2008 Council decided to approve the application
in full subject to conditions.
Details of the decision are as follows:

1     APPLICATION DETAILS

 Application No:                     2008/425
 Street address:                     26 Eenie Creek Road NOOSAVILLE
 Real property description:          LOT: 1 SP: 182880
 Planning Scheme:                    The Noosa Plan

2     DECISION DETAILS
The following type of approval has been issued:
    for Operational Works - Landscaping

3     RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Permit is 2 years (9 May 2010) from the date that this
development approval takes effect.

4     ASSESSMENT MANAGER CONDITIONS

1.    The development shall be carried out in accordance with the approved plans listed below or as
      modified herein.
2.    Prior to the commencement of works, the applicant shall comply with the requirements of the
      Building Construction Industry (Portable Long Service Leave) Act 1991. In this regard, a
      Statutory Declaration outlining the cost of building and construction works, as defined in
      s73.(1) of the Act, shall be submitted in conjunction with an application for Operational Works.
      If payment of the levy is required, the approved forms as outlined in s77.(1), must also be
      sighted by the assessment manager.



                                                                                                   Page 1 of 7
Full text of the other 6 pages

Page 2

                                                -2-



4.    A Traffic Management Plan for the project shall be prepared by suitably qualified persons and
      submitted to Council for approval prior to the pre start meeting. The report shall address, but
      not be limited to, all items listed below:
             4.1 A single nominated access location to / from the site.
             4.2 Provision of safe cycle and pedestrian movements around the first section of Loop
                  Road - LA02.
             4.3 Provision of signage and traffic controllers in accordance with Manual of Uniform
                  Traffic Control Devices and Transport Infrastructure (Roads) Act.
3.    The finished level of all mulch in garden beds and landscaped medians is to be a minimum of
      50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in
      accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
      Guidelines.
4.    The “Hardenbergia violacea” shown on the drawings is not an acceptable species. This
      plant shall be replaced with another species that is in accordance with Council’s Planning
      Scheme Policy PSP03 Landscaping Plants and Guidelines.
5.    Install suitable root barrier where proposed trees are adjacent to paths, pavement etc in
      accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
      Guidelines.
6.    Suitable sediment control devices must be in place prior to works commencing. These devices
      are to be checked and cleaned on a regular basis and specifically after each rain event.
      These devices are to remain in place during the landscaping works of the development.
      The location and type of device to be installed shall be established at the “pre start” meeting
      with Council’s Construction Technical Officer and shall be installed prior to the
      commencement of any works.
7.    Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’
      notice of intention to commence works to arrange a “pre start” meeting prior to the
      commencement of works.
8.    The principal contractor must have all the appropriate insurance and public liability
      documentation to carry out the works. The principal contractor is also responsible to ensure
      that any sub contractors also have the appropriate insurance and public liability
      documentation.
9.    Prior to the “pre start” meeting, the principal contractor must be provided with a copy
      of Council’s signed approved drawings and conditions by the applicant.
10.   Unless advised otherwise, the consulting engineer for this project shall be responsible for
      arranging all inspections, with Council’s Construction Technical Officer or nominated staff.
      Council’s Construction Technical Officer shall provide an inspection form for signing off by the
      engineer at appropriate stages of construction, during on-site meetings. Construction
      Technical Officer will also sign the form at each stage when conditions required have been
      satisfied. The works will be accepted “On Maintenance” after this form, signed by the
      inspector for each stage is complete, together with a letter from the engineer requesting that
      the works go “On Maintenance”.
11.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
      project. (This person will be the contact for the project).
12.   Council standards shall apply to these works unless otherwise modified herein.
13.   The person acting on this permit shall ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property, road pavements or facilities (such as underground drainage, water supply,
      sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected against any
      damage or interference whatsoever.

                                                                                            Page 2 of 7

Page 3

                                                 -3-



      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify the Manager Land Development and shall forthwith rectify the damage to that
      property or facility at its cost and to the satisfaction of the Manager Land Development.
      All rectification works are to be completed prior to the sealing of the survey plan or,
      alternatively, the Applicant may request the Council to carry out the rectification work at the
      Applicant’s cost, such cost being paid by the Applicant to the Council prior to the sealing of the
      survey plan.
      In the case of any emergency the Council shall be entitled to rectify such damage at the cost
      of the Applicant, such cost being paid prior to the sealing of the survey plan.
14.   The development of the site shall be carried out in such a manner as to prevent dust and/or
      sand nuisance to residents and/or tenants in the vicinity of the development.
15.   Construction work and other associated activities are permitted only during the hours of 7.00
      am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays
      except where extended hours are approved by the Manager, Land Development, or his
      nominee.
16.   All signage, including that for safety during construction shall be in accordance with the
      Manual of Uniform Traffic Control Devices and Transport Infrastructure (Roads) Act.
17.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will
      be imposed on construction works during the maintenance period, which is a minimum period
      of 12 months duration. Such bond must be lodged by, and shall only be accepted from the
      Developer for the works.
18.   The works to become Council assets will not be accepted "On Maintenance" until the
      landscaping is completed.
19.   These works are also to be in compliance with the relevant conditions of Development Permit
      No. 2006/1594.
20.   Notwithstanding that Council has checked the plans with due care, where it is found during
      construction that variations from Council's standards exist, then Council standards shall apply.


5     REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Not Applicable.

6     APPROVED PLANS
The approved plans and for this development approval are listed in the following table:
 Plan No.             Rev.     Plan Name                                      Date
 LA01                 A                                                       Feb 2008
                               Site Plan: Land Graphics
 LA02                 A                                                       Feb 2008
                               Landscape Part Plan 1: Land Graphics
 LA03                 A                                                       Feb 2008
                               Landscape Part Plan 2: Land Graphics
 LA04                 A                                                       Feb 2008
                               Landscape Part Plan 3: Land Graphics
 LA05                 A                                                       Feb 2008
                               Landscape Part Plan 4: Land Graphics

                                                                                              Page 3 of 7

Page 4

                                                  -4-



 LA06                  A                                                         Feb 2008
                               Landscape Details: Land Graphics

7      ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
     1. Should any changes or modifications to the approved plans be required as a result of
        construction constraints, a Change to an Existing Approval Application under the Integrated
        Planning Act must be made. Amended plans clearly indicating the changes must be lodged
        with this application along with the appropriate fees.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8      PROPERTY NOTES

Not Applicable.

9      PRELIMINARY APPROVAL OVERRIDING SCHEME
Not Applicable.

10     FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required            Subject of the required Development Permit
 Not Applicable.

11     SELF ASSESSABLE CODES
Not Applicable.

12     SUBMISSIONS
Not Applicable.

13     REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

Not Applicable.
14     RIGHTS OF APPEAL

You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.



                                                                                                 Page 4 of 7

Page 5

                                                -5-



During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).

15    OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.



Yours faithfully



Ron Read
SENIOR TECHNICAL ASSESSMENT OFFICER




                                                                                           Page 5 of 7

Page 6

                                                        -6-




                                              Appeal Rights
                                             INTEGRATED PLANNING ACT 1997 & 1998 REGULATION


                                                                  (4) If an application involves both impact
The following is an extract from the Integrated               assessment and code assessment, appeal rights
Planning Act (Chapter 4).                                     for submitters are available only for the part of the
                                                              application involving impact assessment.
Division 8 - Appeals to court relating to
development applications                                          (5) If an application is processed under section
                                                              6.1.28(2), appeal rights for submitters for the
Appeals by applicants
                                                              application are available only for the aspects of the
4.1.27.(1) An applicant for a development                     development that would have required public
application may appeal to the court against any of            notification under the repealed Act.
the following-
(a) the refusal, or the refusal in part, of a                     (6) If an application involves assessment
    development application;                                  against a concurrence agency code, appeal rights
(b) a matter stated in a development approval,                for submitters for the application are not available
    including any condition applying to the                   against the part of the approval that represents the
    development, and the identification of a code             concurrence agency’s response for the code.
                         1
    under section 3.1.6;                                      Appeals by advice agency submitters
(c) the decision to give a preliminary approval               4.1.29.(1) An advice agency may, within the limits
    when a development permit was applied for;                of its jurisdiction, appeal to the court about the
(d) the length of a currency period;                          giving of a development approval for a
                                                              development application if-
(e) a deemed refusal.
                                                              (a) the development application involves impact
    (2) An appeal under subsection (1)(a) to (d)
                                                                  assessment; and
must be started within 20 business days (the
“applicant’s appeal period”) after the day the                (b) the advice agency told the applicant and the
decision notice or negotiated decision notice is                  assessment manager to treat its response to
given to the applicant.                                           the application as a submission for an appeal.
    (3) An appeal under subsection (1)(e) may be                  (2) The appeal must be started within 20
started at any time after the last day a decision on          business days after the day the decision notice or
the matter should have been made.                             negotiated decision notice is given to the advice
                                                              agency as a submitter.
Appeals by submitters
                                                              Appeals for matters arising after approval given
4.1.28.(1) A submitter for a development
                                                              (co-respondents)
application may appeal to the court about-
                                                              4.1.30.(1) For a development approval given for a
(a) the giving of a development approval, including
                                                              development application, a person to whom any of
    any conditions (or lack of conditions) or other
                                                              the following notices have been given may appeal
    provisions of the approval; or
                                                              to the court against the decision in the notice-
(b) the length of a currency period for the approval.
                                                              (a) a notice giving a decision on a request for
    (2) The appeal must be started within 20                      extension of the currency period for an
business days (the “submitters appeal period”)                    approval;
after the day the decision notice or negotiated
                                                              (b) a notice giving a decision on a request to make
decision notice is given to the submitter.
                                                                  a minor change to an approval.
    (3) If a person withdraws a submission before
                                                                  (2) The appeal must be started within 20
the application is decided, the person may not
                                                                      business days after the day the notice of the
appeal the decision.
                                                                      decision is given to the person.




1
     Section 3.1.6 (Preliminary approval may override
    local planning instrument)
                                                                                                        Page 6 of 7

Page 7

                                                        -7-



    (3) Subsection (1)(a) does not apply if the               Appeals against local laws
        approval resulted from a development                  4.1.33B.(1) An applicant who is dissatisfied with a
        application (superseded planning scheme)              decision of a local government or the conditions
        that was assessed as if it were an                    applied under a local law about the use of premises
        application under a superseded planning               or the erection of a building or other structure
        scheme.                                               permitted by the planning scheme may appeal to
    (4) Also, a person who has made a request                 the court against the decision or the conditions
        mentioned in subsection (1) may appeal to             applied.
        the court against a deemed refusal of the                 (2) The appeal must be started within 20
        request.                                              business days after the day notice of the decision
    (5) An appeal under subsection (4) may be                 is given to the applicant.
        started at any time after the last day the            For Building Works Only
        decision on the matter should have been
        made.                                                 Rights of appeal conferred by Section 4.2.9 of the
                                                              Integrated Planning Act 1997 as follows:
Division 9 - Appeals to court about other
matters                                                       Division 3 – Appeals to tribunals relating to
                                                              development applications
Appeals for matters arising after approval given
(no co-respondents)                                           Appeals by applicants
4.1.31.(1) A person to whom any of the following              4.2.9(1) An applicant for a development application
notices have been given may appeal to the court               may appeal to the Building and Development
against the decision in the notice-                           Tribunal against any of the following-
(a) a notice giving a decision on a request to                (a) the refusal, or the refusal in part, of a
    change or cancel a condition of a development                 development application;
    approval.                                                 (b) a matter stated in a development approval,
                                    2
(b) a notice under section 6.1.44 giving a decision               including any condition applying to the
    to change or cancel a condition of a                          development, and the identification of a code
                                                                                        3
    development approval.                                         under section 3.1.6;
    (2) The appeal must be started within 20                  (c) the decision to give a preliminary approval when a
                                                                    development permit was applied for;
        business days after the day the notice of the
        decision is given to the person.                      (d) the length of a period mentioned in section 3.5.21
                                                                    currency period;
    (3) Also, a person who has made a request
        mentioned in subsection (1)(a) may appeal             (e) a deemed refusal.
        to the court against a deemed refusal of the             (2) An appeal under subsection (1)(a) to (d) must
        request.                                              be started within 20 business days (the “applicant’s
                                                              appeal period”) after the day the decision notice or
    (4) An appeal under subsection (3) may be
                                                              negotiated decision notice is given to the applicant.
        started at any time after the last day the
        decision on the matter should have been                   (3) An appeal under subsection (1)(e) may be
        made.                                                 started at any time after the last day a decision on the
                                                              matter should have been made.
Appeals against decisions to change approval
                                                              The Registrar for the Building and Development
conditions under the repealed Act
                                                              Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a               http://www.localgovernment.qld.gov.au/
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act
may appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice
of the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on
the matter should have been made.

2
     Section 6.1.44 (Conditions may be changed or
                                                              3
    cancelled by assessment manager or concurrence                 Section 3.1.6 (Preliminary approval may override
    agency in certain circumstances)                              local planning instrument)
                                                                                                          Page 7 of 7

Used in these records

About this file

File size
55 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00000425.001 [As Published].pdf · 55 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.