4. A Traffic Management Plan for the project shall be prepared by suitably qualified persons and
submitted to Council for approval prior to the pre start meeting. The report shall address, but
not be limited to, all items listed below:
4.1 A single nominated access location to / from the site.
4.2 Provision of safe cycle and pedestrian movements around the first section of Loop
Road - LA02.
4.3 Provision of signage and traffic controllers in accordance with Manual of Uniform
Traffic Control Devices and Transport Infrastructure (Roads) Act.
3. The finished level of all mulch in garden beds and landscaped medians is to be a minimum of
50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in
accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
Guidelines.
4. The “Hardenbergia violacea” shown on the drawings is not an acceptable species. This
plant shall be replaced with another species that is in accordance with Council’s Planning
Scheme Policy PSP03 Landscaping Plants and Guidelines.
5. Install suitable root barrier where proposed trees are adjacent to paths, pavement etc in
accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
Guidelines.
6. Suitable sediment control devices must be in place prior to works commencing. These devices
are to be checked and cleaned on a regular basis and specifically after each rain event.
These devices are to remain in place during the landscaping works of the development.
The location and type of device to be installed shall be established at the “pre start” meeting
with Council’s Construction Technical Officer and shall be installed prior to the
commencement of any works.
7. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’
notice of intention to commence works to arrange a “pre start” meeting prior to the
commencement of works.
8. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any sub contractors also have the appropriate insurance and public liability
documentation.
9. Prior to the “pre start” meeting, the principal contractor must be provided with a copy
of Council’s signed approved drawings and conditions by the applicant.
10. Unless advised otherwise, the consulting engineer for this project shall be responsible for
arranging all inspections, with Council’s Construction Technical Officer or nominated staff.
Council’s Construction Technical Officer shall provide an inspection form for signing off by the
engineer at appropriate stages of construction, during on-site meetings. Construction
Technical Officer will also sign the form at each stage when conditions required have been
satisfied. The works will be accepted “On Maintenance” after this form, signed by the
inspector for each stage is complete, together with a letter from the engineer requesting that
the works go “On Maintenance”.
11. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
project. (This person will be the contact for the project).
12. Council standards shall apply to these works unless otherwise modified herein.
13. The person acting on this permit shall ensure that its consultants and contractors take all
reasonable care during the construction of the engineering works to ensure that Council
property, road pavements or facilities (such as underground drainage, water supply,
sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected against any
damage or interference whatsoever.
Page 2 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2008.00000425.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 55 KB (small file)
- File type
No other editions are linked here.