Council archive · source document
07/1017 - Response to Info Request [As Published] · 142007.1017
SPECIFICATION
EXTENT OF WORKS
BUSH ROCK SCHEDULE
Contractor should take full account af documentation of Civil Engineering, Hydraulic and Electrical Engineering Works. Landscape works are Small 200-300 mm in any di rection
to include the folowing: Medium 500-600 in any direction LEGEND
EXCAVATION AND DRAINAGE Large 700-800 in any direction
Break up and remove any excess concrete slurry from construction works to achieve required planting depths. Excavate site soil to a depth of
100mm. Break up remaining subgrade to a depth of 10mm. Drainage is to be incorporated to ail planting areas that are enclosed by hard
edging and not otherwise drained. Contractor should allow for overland gravel drains through mulched areas to stormwater catchment pits.
* Bush rock to be smooth/round faced and
free from chips and scraps.
IRRIGATION hall be sed and 1 nde he * Bury all rock generally 1/2 the rock depth.
rigation for the project shall be carried out by an experienced and reputable irrigation contractor - Tenderers intending to h irigation * ‘ j
themselves will be required to demonstrate proficiency in this area, Submit an irigation plan to the site supervisor for approval prior to Rock selection and burying depths to be
installation. A fully automated and programmable irrigation system, with rainswitch, is to be provided to all Garden areas. Al fittings are to be approved prior to installation..
fully effective and inconspicuously placed with lines placed through conduits under hard surfaces. Water connection points will be the water
tanks at the rear of each fot. The system should provide requlated application to all areas with no overspray or runoff onto hard surfaces.
Irrigation systems are to be guaranteed for a period of 12 months against fauity materials and workmanship.
80mm depth gravel as
detailed & specified
Bush boulders as scheduled
Tree planting as scheduled
CPS o Shrubs & Groundcovers as
TOPSOIL - SUPPLY AND INCORPORATION iy scheduled
Planting areas are to be progressively filled with premium grade blended organic garden soil mix to a minimum of 400mm depth. Soil to be an “pre
approved garden organic mix. Soil supplier as well as intended mix is to be nominated. Soil is to be mounded to facilitate good drainage to
2x AUSbb
4x DlAcae
4x MACluc hardstand areas (max 1:3 grade) and 1s To finish 50mm below edging after settement. Organic additive such as Dynamic tifter‘is to be
incorporated throughout the soil mix at the recommended rate. A slow release fertiliser ‘Osmocote’ or equivalent is also to be incorporated
1x DORexc with individual plantings in accordance with the manufacturers recommendations.
EDGING
Provide an extruded concrete edge to all garden beds where adjacent to grass areas. Line of edging to be set out and approved on site prior
2 medium & 1 to construction.
small bush rock
as scheduled SHAPING OF GARDEN AREAS
Planting areas are to be finished in a gently mounded fashion to facilitate drainage of excess water and to show planting to best advantage.
, Vion ASD Contractor is to seek confirmation of finished levels prior to final plantings and application of mulch.
x er
CONTAINERISED PLANT MATERIAL
Plant material is to be approved by superintendent prior to planting. Planting is to be cartied out in a manner consistent with good horticultural
practice. All 300 pot and larger plant material is ta be guyed and staked as per Detail - Advanced Container Planting. Smaller plant stock is to
be staked as necessary. Stakes shall not pass through the rootbail of plant at time of planting or any fime thereafter.
Stock may be rejected if plants are:-
a) Undersized proportional to specified container size or is the roat system if underdeveloped
b) Oversized proportional to specified container size or severely root bound.
c) Unbalanced or uncharacteristic of normal or specified growth pattem for the species.
d) Not suitably acckimatised for the specific environment
) Diseased, infested with pests or suffering from other form of significant sires.
4th FLOOR PLANTING PLAN
Scale 1:100
GARDEN MULCH
PLANT SCHEDULE - Mulch shall be one inch hoop pine muich to predominant depth of 100mm. Mulch is to be graded to avoid placement against green plant
stems and overflow from purpose formed edges, kerbs and pathways.
CODE SCIENTIFIC NAME COMMON NAME SIZE QTy TURF
a) “SIR WALTER" minimum sod depth 25mm
Shrubs b} Turf to be laid within 24 hours of being cut
ALParu = Alpinia arundeliliana Dwarf Ginger 200mm 7 ¢) Allow for ground preparation and deposition of 50mm imported garden loam topsoil
AUSbb = Austromyrtus ‘Blushing Beauty’ Blushing Beauty 200mm 4 d) Turf to be closed butted and rolled in accordance with accepted practice to ensure a smooth even surface
CORrub Cordyline rubra ‘Rea’ Red Palm Lily 200mm 4
DORexc Doryanthus excelsa Gymea Lily 300mm 2 fo eeae a Choon Shavings, supply ad instal exposed aggregate coloured concrete and pavers. Concrete colour, aggregate
i i i i 300mm y + I,
snow Anosha a Hy monosiachy a ny oer oie Zaria 300mm , selection paver selection and installation details as nominated on the plan Paving Schedule. Instalation to follow industry best practices
indudi ion, ion, mini a
XANjoh _ Xanthorrhoea johnsonii Grass Tree <300 trunk 1 induding ground preparation, compaction, minimal slump allowances and minimum joint distances,
GRAVEL - SUPPLY AND INSTALLATION
Tussocks & Ground Covers Supply and install minimum 80mm depth approved 16mm-20mm Cream River Gravel to a compacted sub base to all areas shown on the
ANigem Anigozanthus ‘Bush Gem’ Bush Glow Kangaroo Paw 140mm 6 plan.
PANjas Pandorea jasminoides Pink Bower of Beauty 140mm 3 MAINTENANCE
DiAbre = Dianella brevipedunculata Flax Lil 140: 4
ISOnod _—/solepsis nodosa * Knobby. Club Rush 440mm 2 a) Obtain signoff of all landscape construction works prior ta commencement of the maintenance period. The maintenance period wil not be
ViOhed Viola hederacea Native Violet 440mm 47 deemed to have commenced without signof.
b) Monitor plant performance and stress constantly and take appropriate remedial action. Soil moisture levels are critical during early
establishment
c) Mow turf every 1-2 weeks or as required to ensure turf does nat exceed 80mm height.
d) Prune and shape all shrubs and trees as required. Replace at the contractors cast ail plants which display a loss of condition or are stolen
& vandalised.
e) Monitor irrigation performance and take remedial action where required.
f) Fertilise ail garden beds at completion of maintenance period (12 weeks).
impermeable rigid
membrane lining
timber boxes
AMENOMENTS
a
A | 27.06.07 JS
4x MAClud in
timber pot as
detailed
¢) Contractor shall maintain an up to date written log book to record inspection observations and actions
h) Contractor must obtain signoff of ail landscape works at the completion af the 12 week maintenance period. To obtain signoff al plants
must display health and establishment, mutch must be at the specified depths, irrigation must be in complete working order, timber elements
Stainless steel angle
brackets with ss. coach
must be re-stained within 2 weeks of maintenance completion, electrical elements must be in complete working order, concrete is to be clean
and free of cracks and depressions, turf is to display a healthy dense even sward to 95% cover and generally the landscape must display head bolts connecting
compliance with industry standards. If at the final inspection, the tandscape does not obtain signoff, the landscape contractor must continue to battens
maintain until the landscape is compliant with the above standards.
100x35 Hardwood
timber battens
1 medium & 2
small bush rock
as scheduled
6x ANIgem
b
=
c a d
TIMBER POTS - DETAIL PLAN Scale 1:20 LANDGRAPHICS
LANDSCAPE ARCHITECTS
Principal: Robert J. Burret
2nd Floor Eaplanade and Second Bung, Mar
P.O, Box 18 Maroomdore 4558
landgraphics@ texinat com au
wan. rapnics. com.au
Tet (07) 5443 4044
ronchydora
WALL OF UNIT
1 x PAnjas Far, (07) 5443 4534
2x COR 100mm much 0 pei Sa
4x PAnjas Planter box shown without lining and imported podium
impermeable rigid membrane
lining timber boxes
100x35 Hardwood
timber battens Client
Mr. J CAMERON & Mr. J McCormax
for information purposes. Both topsoil mix in planter boxes
boxes require lining SUNVIEW VILLAS
Stainless steel angle
brackets with ss. coach head
bolts connecting battens.
2 medium & 3
smail bush rock
as scheduled
100mm mulch as
specified & imported Architect
SO
SKS
a
o
BES
Oi
Ok
8 A im
a XO4 podium topsoil mix WILL FRANKLIN DESIGN
SO
WN Drawing Tele
SS Concrete blocks LANDSCAPE PLANTING PLAN,
supporting planter boxes
at their required height DETAILS & SPECIFICATION
NS a . NS if
VSR, f
PERO ROSPVorey
Drainage medium
(by others)
3rd FLOOR PLANTING PLAN Scale 1:100
EDGE OF PODIUM GARDEN BED
Scale 1:20 Jeb No. Dawg sheet:
LA1201 LAQ3 03 OF 03
TIMBER POTS - DETAIL SECTION
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
07/1017 - Response to Info Request [As Published]Related documentApplication case desk ↗
About this file
- File size
- 4.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.