From:                         Scott Josephs
To:                           Shane Adamson
Subject:                      FW: Good Shepherd - MCU20/0072
Date:                         Tuesday, 5 March 2024 4:20:36 PM
Attachments:                  image004.png
                              FW Modular DA Info Request.msg



Hi Shane,

Here’s the email from Patrick agreeing to the 1150. As discussed this was never made official as we pulled out of the process. I’ve
also included an email from Anthony that was part of our RFI package for the demountables. It’s potentially where the 1105 came
from, NC asked for current enrolments and future maximum, our response was 1105 is current, 1150 is maximum.

From: Patrick Murphy <[email protected]>
Sent: Friday, December 17, 2021 11:35 AM
To: Scott Sobey <[email protected]>
Subject: Good Shepherd - MCU20/0072

[CAUTION]: This email originated from outside of the organisation. Do not act on instructions, click links or open attachments unless you recognise the
sender and know the content is authentic and safe.
Good morning Scott,

The proposed updated conditions are detailed below with a draft Deed of Variation also attached.

Based on your general acceptance of the draft Deed of Variation we would be seeking for a legal review at the applicant’s expense.

Regards
Patrick

Patrick Murphy
Coordinator Planning I Development Assessment
Environment and Sustainable Development I Noosa Council

Phone:         07 5329 6436
                           


Email:    [email protected]
Website:    www.noosa.qld.gov.au
Location: Level 2, 9 Pelican Street, Tewantin
Mail:         PO Box 141 Tewantin Qld 4565
Find Council on Facebook



1.         ASSESSMENT MANAGER CONDITIONS

PLANNING
    When Conditions must be Complied With
1.         Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and
          then compliance maintained at all times while the use continues.
          Approved Plans
2.         Development undertaken in accordance with this approval must generally comply with the approved plans of
      development. The approved plans are listed in the following table unless otherwise amended by these conditions.
       Plan No. Rev.     Plan/Document Name                                 Date
       SK-01     P1      Location Plan prepared by Burling Brown            01.07.2020
                         Architects
       SK-02     P3      Proposed Site Plan prepared by Burling Brown       20.07.2020
                         Architects
       A-000     I       Schedules – Building Shell (MQB) prepared by       15.07.2020
                         Ausco Modular
       A-001     I       Site Plan (MQB) prepared by Ausco Modular          15.07.2020
       A-100     I       Site Plan (MQB) prepared by Ausco Modular          15.07.2020
       A-101     I       Roof Plan (MQB) prepared by Ausco Modular          15.07.2020
       A-200     I       Elevations (MQB) prepared by Ausco Modular         15.07.2020
                         Concept plan detailing upgrade of the existing
                         drop-off/pick-up / carpark configuration
                         Plan detailing options for internal vehicular link
      Amenity
3.         The development must be undertaken and operated in a manner that causes no detrimental effect upon the amenity of the
           neighbourhood by reason of the creation of excessive noise, lighting nuisance or other emissions.
4.         Any advertising sign or device is to comply with the provisions of Council's policies on advertising.
      Nature and Extent of Approved Use
5.         The approved demountable buildings must only be used to service current enrolments and must not be used to facilitate
           an increase in enrolments.
6.         The number of students must not exceed 1150.
7.         A minimum of 328 car parking spaces must be provided. This must include the 128 car parking spaces on Lot 1 SP
Log in to download the original file

RFI - Attachment 5B - Email from NC MCU20-0072.pdf · 1.5 MB (small file)

Full text of the other 2 pages

Page 2

     228052 which are accessed from Goodchap Street as identified in the diagram below:




     Currency Period
8.         This development approval lapses if the use has not happened by 20 August 2027, unless an application to extend the
          currency period is approved by Council.
          Land Amalgamation
9.         Lot 1 on SP228052 and Lot 30 on SP170751 must be amalgamated.
            Traffic
10.      The drop off/pick up/ carpark configuration, accessed from the Goodchap Street/Eumundi Noosa Road roundabout entry,
         as detailed in the approved plans must be upgraded in accordance with an Operational Works approval.
11.      An internal one-way vehicular link from the new staff car park to the Goodchap Street/Eumundi Noosa Road roundabout
         exit as detailed in the approved plans must be provided in accordance with an Operational Works approval.
12.      The applicant/owner may enter into a written agreement with Council to delay the commencement of the works required
         by conditions 10 and 11 as follows:
     a)    Condition 10 until 31 December 2022
     b)    Condition 11 for 18 months subject to a detailed traffic impact assessment being submitted to Council within 12
         months of the commencement of the use to support a request to delete the requirement for these works and the
         requirement to maintain 50 spaces in the location specified by the diagram in condition 7.
     The terms of the agreement must be on terms acceptable to Council, prepared at the cost of the owner, and executed by
     the parties prior to the use commencing.
ENGINEERING
     Stormwater Drainage
13.      The site must be provided with a stormwater drainage system connecting to the existing school drainage system and the
         lawful point of discharge.
14.      Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to
         the asset owner at the following times:
     a.         where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
     a.         where otherwise, upon completion of the works associated with the development.
     Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant
     service authority for approval.




From: Scott Sobey <[email protected]>
Sent: Wednesday, 27 October 2021 11:18 AM
To: Patrick Murphy <[email protected]>; Kerri Coyle <[email protected]>

Page 3

Subject: Good Shepherd - MCU20/0072

External sender. Do not open links or attachments if the email is unexpected or unusual or impersonates staff.


Hi Patrick & Kerri

As discussed have reviewed conditions 10 – 12.

Suggested revision to Conditions 10 & 11 as below with condition 12 becoming redundant as result and could be deleted.

10. The drop off/pick up/ carpark configuration, accessed from the Goodchap Street/Eumundi Noosa Road roundabout entry as
detailed in the approved plans must be upgraded in accordance with the requirements of the Deed of Agreement entered into
with Council and an Operational Works approval. Timing for completion of the works is not required prior to commencement of
the use and is to be in accordance with the Deed of Agreement

11. An internal one-way vehicular link from the new staff car park to the Goodchap Street/Eumundi Noosa Road roundabout
exit as detailed in the approved plans must be provided in accordance with the requirements of the Deed of Agreement entered
into with Council and an Operational Works approval, unless it is agreed by Council under the Deed of Agreement provisions
that the works are not required. Timing for completion of the works is not required prior to commencement of the use and is to
be in accordance with the Deed of Agreement

Regards



                    Scott Sobey
                    Director | Project Urban
                    P | 07 5443 2844 M | 0400 775 835
                    W | projecturban.com.au




.


Disclaimer

The information contained in this communication from the sender is confidential. It is intended solely for use by the recipient
and others authorized to receive it. If you are not the recipient, you are hereby notified that any disclosure, copying, distribution
or taking action in relation of the contents of this information is strictly prohibited and may be unlawful.




This email transmission is confidential and intended solely for the person or organisation to which it is addressed. If you are not the intended recipient, you must not copy, distribute or
disseminate the information, or take any action in reliance of it. Good Shepherd Lutheran College accepts no liability for the content of this email, or for the consequences of any actions taken
on the basis of the information provided, unless that information is subsequently confirmed in writing. Good Shepherd Lutheran College does not accept liability for any damage caused by any
virus transmitted by this email. Security of this e-mail transmission cannot be guaranteed or error-free as information could be intercepted, corrupted, lost, destroyed, arrive late or incomplete,
or contain viruses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.