Council archive · source document
17494 SARA Early Referral · OPW20/0237
2010-19429 SER
Attachment 1—Conditions to be imposed
No. Conditions Condition timing
Operational works – Tidal works in a coastal management district
Tidal works or work in a coastal management district—The chief executive administering the Planning
Act 2016 nominates the Director-General of the Department of Transport and Main Roads to be the
enforcement authority for the development to which this development approval relates for the
administration and enforcement of any matter relating to the following condition(s):
1.
The development must be carried out generally in accordance with At all times
the following plan:
Site plan prepared by Superior dated 18 August 2020,
reference 17494-D01, Revision A
Pontoon plan prepared by Superior dated 18 August 2020,
reference 17494-D02.
2.
The structure must be lit/marked in accordance with the following At all times
specifications, such that it does not cause a risk to the safe
navigation of other ships:
section 3 of AS4282-1997 Control of the obtrusive effects of
outdoor lighting.
3.
The construction, operation or maintenance of the structure, and any At all times
ship berthed, moored or attached to the structure, must not:
(a) encroach into, pass over or under a navigation corridor or
(b) be located in a high risk maritime zone.
4. Any debris or similar obstruction generated whilst undertaking the
While works are
work must be removed from the waterway and suitably disposed of
occurring
at the applicant’s expense.
5. All piles and/or structures to be demolished, both above and below Prior to the completion
the waterline must be completely extracted/removed. of the works
Tidal works or work in a coastal management district—The chief executive administering the Planning
Act 2016 nominates the Director-General of the Department of Environment and Science Coastal
Assessment to be the enforcement authority for the development to which this development approval
relates for the administration and enforcement of any matter relating to the following condition(s):
6.
The construction of the pontoon must be undertaken generally in For the duration of
accordance with the following plan: works and to be
maintained
Site plan prepared by Superior dated 18 August 2020,
reference 17494-D01, Revision A
Pontoon plan prepared by Superior dated 18 August 2020,
reference 17494-D02.
State Assessment and Referral Agency Page 3 of 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
17494 SARA Early Referral.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.2 MB (small file)
- File type
No other editions are linked here.