Council’s Reference: OPW19/0082 Our Reference: 02498 L07 NG Our Contact: Nadine Gorton 9th March 2020 Chief Executive Officer Noosa Council PO BOX 141 TEWANTIN Q 4565 ATTENTION: DEVELOPMENT ASSESSMENT Dear Sir/Madam, RE: MINOR CHANGE – ADDITIONAL INFORMATION Change to an Existing Development Approval (TPC1903 – 25 Tourist Villas, 2 Managers Residences and Community Hall) for premises at 396 Lake Cooroibah Road, Cooroibah and described as lot 0 and Lot 2 on GTP 1928. I refer to the above application lodged with Council and Councils email dated 14th May 2019. My client has reviewed the matters raised in the email and wishes to provide additional proposal plans, landscape plans and engineering reports. My client also wishes to respond to the matters in the email as follows: 1. Cover Letter – owners consent In accordance with section 79 of the Planning Act, a change application must be accompanied by the written consent of the owner of the premises the subject of the application to the extent: (a) the applicant is not the owner; and (b) the application is in relation to— (i) a material change of use of premises or reconfiguring a lot; or (ii) works on premises that are below high-water mark and outside a canal; and (c) the premises are not excluded premises. The Planning Act defines an owner of land as: owner, of land, premises or a place, means the person who— (a) is entitled to receive rent for the land, premises or place; or (b) would be entitled to receive rent for the land, premises or place if the land, premises or place were rented to a tenant Mr Brian Williams advises that he is the owner of Lot 2 and therefore the owner of the lot which is the subject of the application. Mr Williams advises that the proposal plans detail that no works are to be undertaken in the common property and therefore body corporate approval is not required.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 3 pages
Page 2
Page 2
2. Application details
As detailed above, all works are to be undertaken within Lot 2 and no works are proposed to be
undertaken in the common property. The applicants engineers indicate that all stormwater will be
contained in Lot 2 and effluent connected to existing systems on site. The existing vehicular access for
the site will be utilised with all car parking associated with the use located on Lot 2.
3. Proposal Report
The applicant submits revised proposal plans and engineering plans that detail all works being located
wholly within Lot 2. The revised the proposal plans detail:
A reduction in the size of the proposed cabins
Removal of the reception building
Minor re-arrangement of cabin location
All stormwater water works to be contained within Lot 2
Advice from Council dated 25th July 2013 states that a new site plan was approved as part of an
infrastructure agreement approved in April 2007. An extract of the approved site plan and the proposed
plan is detailed below:
2007 Approved Plan Proposal Plan
Differences between the proposal plans are detailed in the table below:
Page 3
Page 3
Existing Approval Proposal
Lot 1 – 6 cabins, community facility and Lot 1 – no changes
managers
Lot 2 – 19 cabins, reception/ caretakers Lot 2 – 19 cabins, caretakers and central BBQ
residence facility
All cabins - GFA 100m2 and 2 bedroom Couples cabin x 4 - GFA 37.8m2
Family cabin x 15 – GFA 43.48m2
Community Facility – GFA 340m2 Removed and replaced with a BBQ shelter with
an area of 99.6m2
Reception/ Caretakers - GFA145m2 Reception/Caretakers/Managers residence – no
detail provided
Managers Residence – GFA 315m2 Located on Lot 1 - no change
Carparking – 23 carports 1 covered space for proposed Managers
- 4 uncovered Residence. All other carparking to be located at
- 2 disabled front of site.
No change to Lot 1
Sewage area approved at front of site Sewage area approved at front of site to be
rebuilt after fire
Water tank approved at front of site Water tanks to be rebuilt after fire
Access from Lake Cooroibah Road Access from Lake Cooroibah Road to be
maintained.
The proposal has been assessed against the Minor Change requirements of the Planning Act and the
Substantially Different development requirements of the DA Rules in the original Planning Report
submitted with the application. The amended proposal has been reviewed against the requirements with
the following noted:
dramatically changes the built form in terms of scale, bulk and appearance; - The existing
approval details 19 tourist villas/cabins on Lot 2 and 6 tourist villas/cabins on Lot 1. No changes
are proposed to the number of cabins on the site. The proposal substantially reduces the size
of the cabins from 100m2 to be between 37m2 and 44m2. The revised proposal also introduces
one and two bedroom cabins whereas the existing approval permitted 2 bedroom units for the
entire development.
The proposed changes therefore do not dramatically change the built form and provide a design
that is more suited to the character of the area.
The cabins are in a different configuration to the approved site plan (which proposed rows of
cabins across the site), however the proposed layout and restriction of vehicles throughout the
site enables greater landscaping between the buildings reducing the appearance of the
development on the surrounding area.
changes the ability of the proposed development to operate as intended; – the proposed
changes to the style and design of the cabins and reduction in built form does not impact on the
operation of the site. The new cabins will be able to be used for visitor accommodation.
introduces new impacts or increase the severity of known impacts; - No new uses proposed on
the site and the proposed alterations to the design and layout provide a smaller built form across
the site. Carparking has also been consolidated and located in one area to the front of the site
reducing the number of vehicles travelling down the existing driveway and to encourage walking
around the site.
Page 4
Page 4
Two pools are detailed as part of the changes to the plans. These pools are ancillary to the proposed
use and are located to the centre of the site away from adjoining properties and will not impact on
surrounding areas. The impacts of construction of the pools are minimal and able to managed as part
of operational works applications.
4. Bushfire Hazard
The proposal plans have been prepared by a professional Bushfire consultant who determined that the
site can comply with State Planning Policy requirements.
5. Proposal Plans
As previously detailed the proposal plans have been amended and all works are now located on lot 2.
The applicant considers that he has now responded to Council’s information request. The Decision
Making Period has therefore commenced and we request that your Council proceeds with its
assessment of the application as soon as possible in accordance with the Planning Act 2016.
Please contact our Sunshine Coast office if you require any further information and/or clarification.
Yours faithfully,
Nadine Gorton
Senior Planner
martoo consulting pty ltd
Used in these records
RFI 9.3.20 - L07 Add info Minor change.pdfRelated documentApplication case desk ↗
About this file
- File size
- 575 KB (small file)
- File type
No other editions are linked here.