Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

Pensar Environmental & Waste Management Plan

Attached to the e-mail Operation Works Application - OPW19/0266 - 215 David Low Way, Peregian Beach (EMAIL 3/3) - Fauna Management, Landscaping, Bushfire Management, Environmental Management, Waste & Preliminary Construction Management Plan.

of 26

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                        Environmental Management Plan

      •   Pensar vehicles are to ensure “Idling time” is kept to a minimum. All vehicles visiting the site are
          to turn their engines off once parked.
      •   Waste will be recycled where possible.
      •   Where an Erosion and Sediment Control Plan (ESCP) has been developed for the project, its
          compliance will be maintained.
      •   Any environmental incidents (including breaches) will be reported and discussed. Causes will be
          identified so that preventative measures can be put in place.
      •   Causes of environmental incidents or breaches are identified and acted upon within 5 working
          days of an incident or breach arising (and where appropriate, before the relevant work activity is
          recommenced).

1.7        Environmental Aspect Identification & Risk Assessment
All relevant environmental aspects are identified, their potential for causing environmental harm is
assessed, and control measures that minimise the potential for environmental harm are defined and
effectively implemented. This information is captured in:
Appendix A: Table of Environmental Aspects / Environmental Risk Assessment
The Risk Management Procedure (WHS-PRO-003) defines the process to be used for identifying the
environmental aspects involved with all work activities in a project and for assessing the level of risk and
potential for environmental harm associated with each environmental aspect, so as to facilitate definition
and implementation of appropriate control measures for every component of each work activity.
The Risk Management Procedure also defines the processes used for involvement of all relevant
personnel (including sub-contractors) in definition and implementation of control measures, and for
monitoring and review to ensure effective implementation of them.
The following tools have been used in accordance with this procedure to identify high risk construction
activities and significant environmental aspects and to define all necessary control measures for this
project:
      •Hazard Identification & Risk Assessment – Projects Form (WHS-FRM-015)
      •Risk Assessment (WHS-RA-004) Risk Assessment - Projects and the Risk Assessment
       Calculator in it.
The completed forms are filed as per “Folder Structure: Site Office” (Section 1.3) of the Project
Management Plan.
All significant environmental aspects with potential for causing environmental harm are listed in:
Appendix B:Significant Environmental Aspects and Impacts
The aspects are hyperlinked to relevant legislation listed in
https://www.enviroessentials.com.au
Pensar does not communicate externally its significant environmental aspects unless directed by the
Client or an Authority.

2.         Project Specific Data
2.1        Measuring Equipment
The equipment listed below is to be used on this project for measuring environmental parameters in
accordance with the relevant control measures:
      -   Environmental Measuring and Testing Equipment will be utilised as required and will be assessed
          on a case by case basis.
Measuring equipment is to be used and calibrated in accordance with the principles defined in the
Management of Plant and Equipment Procedure (PLT-PRO-001) and in accordance with the
manufacturer’s instructions. Specialist equipment calibration agents are engaged as required for
calibration of this measuring equipment.


 Environmental Management Plan (ENV-PLN-001-G20-010)                                       April 2019, Rev: 10
 215 David Low Way, Peregian Beach/ G20-010                                                    Page 7 of 15
Log in to download the original file

Pensar Environmental & Waste Management Plan.pdf · 1.0 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.