2009/578
24.4 Provision of safe cycle and pedestrian movements in the vicinity of the development
on Park Road.
24.5 No queuing of trucks is permitted on residential streets, especially prior to 7.00am.
Further parked trucks must have engines turned off.
24.6 Provision of signage and traffic controllers in accordance with Manual of Uniform
Traffic Control Devices and Transport Infrastructure (Roads) Act.
24.7 Provide an indication where the surplus spoil is to be transported to, and/or source of
imported fill material.
24.8 Traffic control is to be provided so that there are no delays to the general traffic using
Park Road.
25. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
installed into the first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each
rain event.
These devices are to remain in place during the civil works and construction phases of the
development.
The location and type of device to be installed shall be established at the “pre start” meeting
with Council’s Construction Technical Officer and shall be installed prior to the
commencement of any works.
26. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’
notice of intention to commence works to arrange a “pre start” meeting prior to the
commencement of works.
27. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any sub contractors also have the appropriate insurance and public liability
documentation.
28. Prior to the “pre start” meeting, the principal contractor must be provided with a copy
of Council’s signed approved drawings and conditions by the applicant.
29. The Consulting Engineers for the project shall be currently Registered Professional Engineers
of Queensland (RPEQ). The Consulting Engineers are responsible for arranging all
inspections with Council’s Construction Technical Officer or nominated staff.
30. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
project. (This person will be the contact for the project).
31. An inspection is to be carried out with the relevant Council officers, the Contractor and
Supervising Engineer after building footprints have been established, and prior to clearing
being carried out. This inspection is to deal with the limits of clearing to be carried out for this
development. This meeting is to take place prior to the “Pre-start” meeting.
32. Council standards shall apply to these works unless otherwise modified herein.
33. The person acting on this permit shall ensure that its consultants and contractors take all
reasonable care during the construction of the engineering works to ensure that Council
property, road pavements or facilities (such as underground drainage, water supply,
sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected against any
damage or interference whatsoever.
Page 4 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001AB810.001.pdfRelated documentPublic source context ↗
Decision Notice - 010.2009.00000578.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 66 KB (small file)
- File type
No other editions are linked here.