INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 23 JUNE 2015
5. Trial Evaluation – Independent Consultant
Pitt & Sherry Pty Ltd have been appointed as the independent consultant to analyse the trial
outcomes. An initial workshop to discuss key performance indicators was held on May 29. A draft
evaluation plan from the consultant is due in mid–July and will be reported to Council at a future
Committee Meeting
Previous Council Consideration
Ordinary Meeting, 9 April 2015, Item 4, Page 8
That Council note the report by the Director Planning & Infrastructure to the General Committee
Meeting dated 7 April 2015 and:
A Note the pre-feasibility study report prepared by consultants GHD Pty Ltd, provided at
Attachment 1 to the General Committee report;
B. Based on the findings of the report, approve the commencement of a six month live trial of
electric buses in Noosa during the 2015/16 financial year:
1. In a 50:50 cost sharing partnership with the Department of Transport and Main
Roads, TransLink Division;
2. Covering the existing 627 Tewantin – Sunshine Beach bus route;
3. Leasing up to 3 x Optare 10 metre electric buses based on the submitted pricing in
the GHD report; and
4. Facilitating the installation of suitable charging infrastructure to support the live
trial.
C. Authorise the CEO to negotiate with TransLink, Sunbus and Optare regarding the
implementation, monitoring and reporting of the live trial; and
D. Approve the funding of the live trial to a maximum of $550,000 to be met from the Public
Transport Levy Reserve.
Finance & Risk
The total 2014/15 & 2015/16 budget for the Electric Bus Trial is $560,000. Costs spent or
committed to date include:
Item Amount
(excl GST)
Livery Artwork $436
Pitt & Sherry Evaluation $65,237
2 x Quick Charge Units $77,000
Shipping (air freight) $10,000
Quick Charge Infrastructure connect and installation $18,500
Energex fee (application upgrade network) $2,200
Civil Works (line marking, bollards ,landscaping trenching, slabs & two unit frames) $20,000
This expenditure is jointly funded by Council and TransLink, with Council’s funding being
provided through the Public Transport Levy
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.