RFI Eng response notice items 4-19 MCU150111
Attached to the e-mail MCU15/0111 Response to information request - 2-4 Lamonts Rd & 19 Trading Post Rd, Cooroy - email 1 of 2.
6 of 8
Item 12 Provide calculations for “Developed site only with Mitigation”.
Our Response
It is our view that inclusion of external catchments in the MUSIC model provides a more accurate assessment of the
treatment performance. A revised version of Table 4-6 of Report B14158.W-03A is presented below. Note the MUSIC
model was revised to account for a change to carpark areas in Sub-catchment F5, as per Palm Lake Resort Drawing C0-
000-2014 Rev H.
From the Table below, the pollutant load reduction targets have been calculated for the developable area of the site.
MUSIC modelling indicates that the proposed treatment train provides a reduction of pollutant loads greater than what is
required. Since the load retained on site is in excess of the targets, the treatment train is considered to be meeting the
water quality objectives.
Table 4-6 MUSIC Modelling Results
Description Pollutant Load (kg/year)
TSS TP TN GP
Developed Site Only (Without Mitigation) 23200 57.3 406 3910
WQOs (Percentage Reduction) 80% 60% 45% 90%
Load Reduction Target 18560 34.38 182.7 3519
Developed Site plus External Catchment (Without Mitigation) 29700 69.20 456 4150
Developed Site plus External Catchment (With Mitigation) 10200 34.60 269 381
Load Retention Achieved 19500 34.6 187 3769
Load Retention Achieved as % of Developed Site Load 84% 60% 46% 96%
Water Quality Objective Achieved (SPP 4/10) YES YES YES YES
Developed Site without External Catchment (With Mitigation) 15370 29.10 177.0 3529
Item 13 To reduce pressure on the pond, demonstrate whether there is any opportunity to retrofit a water quality
treatment facility within the road reserve or other location within the development so that any activities on the
road system will not be attributed directly to any issues within the pond system.
Our Response
Flows are to be pre-treated prior to entering the central WQCP via bioretention basins. It appears that a flow split pit on
Drawing B14158.W Sheet SK101 was not recognised. This plan has been updated for clarity.
Item 14 Provide the Music Model and Auto Cad files or other mechanism to demonstrate that proposed nodes
and impervious areas are consistent with development plans.
Our Response
The areas of imperviousness was reviewed for each park node in the MUSIC model. The park node for catchment F3 has
15% imperviousness. The park nodes for catchments E1, F1, F2, F3, F5 have 0% impervious, however these catchments
are relatively small and do not need additional imperviousness as this area is captured in separate nodes. Refer attached
plan B14158.W Sheet SK112 which indicates areas of imperviousness.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.