EMP – CONSTRUCTION PHASE 4-2
4.1 Element C.1: Legislative Compliance
Policy: To ensure all design, supervision and actions undertaken in conjunction with the
development of the Settlers Cove site are undertaken in accordance with all relevant
Council and state government legislation, policies and conditions of approval.
Strategy: Identify all applicable legislation, policies and conditions of approval applying to
the development and provide a reference copy on site
Responsibility: Superintendent and Site Environmental Officer.
Management Actions:
1. Establish and maintain a register of all conditions that apply to the site.
2. Identify all relevant pieces of legislation and Council Policies/Local Laws and identify
implications for development of the project. Each element (C.2-C.15) has indicated the applicable
legislation/policy/condition.
3. Monitor any change in policy, conditions and relevant legislation and amend specific elements in
EMP as required.
4. Amend compliance requirements if necessary.
Performance Requirement:
• Register to be established prior to construction commencing on site.
• Register to be updated as required in response to changes in policy or legislation.
Monitoring: SEO to actively monitor changes in liaison with Council. Superintendent to review at 3
monthly intervals to ensure all is up to date.
Reporting: Include any changes in monthly reporting.
Corrective Action: Update register.
G:\ADMIN\B15184.G.DAH\R.B15184.001.05..DOC 22/7/05 10:07
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.