RFI - Ecological Assessment Report

of 435

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file (67.6 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 248, section 1. The text section number identifies this passage in the reader.

EMP – CONSTRUCTION PHASE                                                                                      4-14

       Strategy:              To ensure that erosion and sedimentation is adequately controlled during the
                              construction phase.

              •      Stormwater is treated as close as possible to the source (as opposed to at the lower areas of
                     the catchment);
              •      Clean stormwater is to be diverted around construction areas of the site including any waste
                     or chemical storage areas, stockpiles and toilets;
              •      All surface runoff shall be directed through temporary control measures to minimise
                     potential for sediment transport off-site;
              •      Any sediment control measures are to avoid significant trees and retained vegetation;
              •      Any catch drains flows are directed through temporary control measures and toward
                     sedimentation ponds;
              •      Any catch drains will be protected from scour by check dams or similar devices aimed at
                     reducing water velocities;
              •      Installation of controls on the upstream and downstream side of any stockpiles or fill
                     embankments;
              •      Removal and appropriate disposal of deposited material, litter and gross pollutants;
              •      Inspections of erosion and deposition is to be conducted on a weekly basis and following
                     storm events that have the potential to cause erosion i.e. normally events with a rainfall
                     intensity greater than 25mm/hr or daily events with totals greater than 50mm.
              •      Erosion and sediment control measures will be implemented in areas prior to
                     commencement of any construction activities. This includes:
                        a. Designating areas for machinery and construction material storage (as required) away
                           from drainage paths;
                        b. Such storage areas are to be suitably bunded and lined to prevent seepage of
                           contaminants into the sand substrate (see C.15);
              •      Education of site personnel through the Induction/Environmental Awareness training;
              •      Construction of sedimentation detention areas as required;
              •      Installation of vehicle washdown facility at site access points to minimise potential for
                     transport of sediment off site; and
              •      No sediment and erosion control devices and water quality control measures are to be
                     located within habitat protection areas (refer approved E&SC drawing provided by
                     Superintendent).
              •      The use of mulch for erosion control is described in the Landscape Master Plan including
                     the use of Hoop Pine bark for slopes greater than 1:3.

        Performance Requirement:
              •      To ensure measures taken to reduce risk of erosion are in accordance with best practice
                     guidelines (I E Aust 1996), minimise the generation of sediments and prevent off-site
                     transport of sediments during construction.


        G:\ADMIN\B15184.G.DAH\R.B15184.001.05..DOC 22/7/05 10:07
Log in to download the original file

RFI - Ecological Assessment Report.pdf · 67.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.