EMP – CONSTRUCTION PHASE 4-29
Strategy: To ensure all measures are taken to prevent unnecessary accidents involving
Employees or the public in the vicinity of the construction site and to minimise
nuisance to residents living around and adjacent to the construction site.
3. A dilapidation study (including photographs) shall be made of Grant Street and Serenity Close
prior to and at the completion of construction works. This study should be submitted to Council
at the pre-start meeting.
Road Closures
1. Prior to any temporary full or partial road closures the principal contractor shall make
application to Council and/or Queensland Police for relevant approvals. Such applications shall
include the detailed traffic management plan. Closures shall not take place until such a time as
all relevant approvals are gained and conditions complied with.
2. During any temporary full or partial road closures the Principal Contractor shall employ
appropriately qualified traffic control personnel to implement approved traffic control measures.
3. Any affected residents shall be notified in writing a minimum of 24 hours prior to any temporary
full or partial road closures in accordance with this EMP and traffic management plan.
Carparking
1. All Contractors, subcontractors and their employees shall park private vehicles within the
construction areas as shown on approved drawing as advised by the Superintendent (see Element
D.3).
2. Parking within Habitat Protection Areas is forbidden.
3. Parking along Banksia Avenue and Serenity Close (existing formation) is not permitted.
4. Temporary carpark areas shall be lined and bunded in accordance with Element C.5 of this EMP.
Construction Sequence
The construction sequence that will apply to the Principal Contractor for the RHD area is described in
the following table.
G:\ADMIN\B15184.G.DAH\R.B15184.001.05..DOC 22/7/05 10:07
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.