Log in to see the plans as drawnR0386A: NAMBOUR LANDFILL - STORMWATER MANAGEMENT PLAN
5 SITE INSPECTION AND MONITORING
Site inspections and monitoring is to be undertaken as detailed below.
SMPs should be considered live documents that in some instances will require review and updating as site conditions
change, or if the adopted measures fail to achieve the required treatment standard.
When a site inspection detects a notable failure in the adopted drainage or other ESC measures, the source of this failure
must be reported, investigated and appropriate amendments made.
Best practice site management requires all ESC measures to be inspected at the following frequencies and include the
following checks as a minimum:
Daily site inspections (during rainfall)
+ All drainage, erosion and sediment control measures
+ Occurrences of excessive sediment deposition (whether on-site or off-site)
+ All site discharge points (including dewatering activities as appropriate)
Weekly site inspections (even if work is not occurring on-site)
+ All drainage, erosion and sediment control measures
+ Occurrences of excessive sediment deposition (whether on-site or off-site)
+ Occurrences of litter or sediment placed, deposited, or washed from the site, including deposition by vehicular
movements
+ Oil, fuel and chemical storage facilities
Following runoff producing rainfall (within 18 hours of rainfall event)
+ All drainage, erosion and sediment control measures
+ Occurrences of excessive sediment deposition (whether on-site or off-site)
+ Occurrences of litter or sediment placed, deposited, or washed from the site, including deposition by vehicular
movements
Environment. Engineering. Education. PAGE 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.